5718 N BEVIS AVE 91411
Certificate Information: 5718 N BEVIS AVE 91411
- Application / Permit
- 25016-10000-10377
- Plan Check / Job No.
- B25LA13233
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. CONVERT EXISTING DETACHED GARAGE TO ADU PER STATE LAW AND GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 9/30/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/19/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2025 | FERNANDO FLORES |
| Corrections Issued | 4/10/2025 | FERNANDO FLORES |
| Applicant returned to address corrections | 6/7/2025 | FERNANDO FLORES |
| Applicant returned to address corrections | 6/18/2025 | ZAW HAN |
| Applicant returned to address corrections | 6/25/2025 | ZAW HAN |
| Plan Check Approved | 8/14/2025 | FERNANDO FLORES |
| Issued | 9/30/2025 | APPLICANT |
| CofO in Progress | 5/19/2026 | VINCENT HANLEY |
Permit Application Clearance Information
| Address approval | Cleared | 4/21/2025 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 4/21/2025 | JILVER MAZARIEGOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2025 | JILVER MAZARIEGOS |
| Construction near power lines | Cleared | 8/2/2025 | ENRIQUE ACOSTA |
Contact Information
| Contractor | D K R Construction Inc; Lic. No.: 1070450-B | , |
| Engineer | Kaballo,, Amir; Lic. No.: C90707 | 20984 UPTOWN AVE #112 BOCA RATON, FL 33428 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/17/2025 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 10/28/2025 | Approved | RYAN SALAZAR |
| Sewer | 11/5/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/18/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 11/18/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 11/18/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/11/2025 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 12/17/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 12/17/2025 | Approved | RYAN SALAZAR |
| Insulation | 12/17/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 12/17/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 12/22/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/22/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 12/24/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 2/20/2026 | Corrections Issued | KIRK SANDERS |
| Final | 2/20/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 2/20/2026 | Approved | KIRK SANDERS |
| HVAC-Final | 2/20/2026 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 2/20/2026 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/20/2026 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 2/20/2026 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 2/24/2026 | Approved | DAVID MATSON |
| Gas Test | 2/24/2026 | Approved | DAVID MATSON |
| PLUMBING-Final | 2/24/2026 | Approved | DAVID MATSON |
| Final | 5/18/2026 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 5/18/2026 | Approved | VINCENT HANLEY |