6102 W 74TH ST 90045

Certificate Information: 6102 W 74TH ST 90045

Application / Permit
25016-10000-10282
Plan Check / Job No.
B25LA13112
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GC66323(a)(1).
Permit Issued
Issued on 7/30/2025
Issuing Office
Current Status
Issued on 7/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/7/2025 APPLICANT
Assigned to Plan Check Engineer 4/9/2025 ROSENDO MEDINA
Corrections Issued 4/10/2025 ROSENDO MEDINA
Plan Check Approved 7/28/2025 ROSENDO MEDINA
Issued 7/30/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 7/3/2025 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 7/9/2025 JESUS CISNEROS
Specific Plan Cleared 7/17/2025 PEDRO AYALA
Address approval Cleared 7/22/2025 JESUS CISNEROS
Grading Pre-Inspection Cleared 7/28/2025 ROSENDO MEDINA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/21/2025 Approved RUBEN RIVAS
PLUMBING-Rough 9/2/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 9/11/2025 Approved RUBEN RIVAS
ELECTRICAL-Rough 11/12/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Approved JESUS PINEDA
HVAC-Rough 11/12/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 11/12/2025 Approved JESUS PINEDA
Underground Mechanical 11/12/2025 Partial Approval JESUS PINEDA
Rough-Elec/Plmb/HVAC 12/4/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 12/8/2025 Approved ANTHONY EGSON
Green Building Rough 12/8/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/8/2025 Approved ANTHONY EGSON
Insulation 12/9/2025 Corrections Issued JESUS PINEDA
Drywall Nailing 12/15/2025 Approved JESUS PINEDA
Insulation 12/15/2025 Approved JESUS PINEDA
Shower Pan 1/2/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 1/6/2026 Approved JESUS PINEDA
ELECTRICAL-Final 2/11/2026 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 5/1/2026 Approved JESUS PINEDA
Final 5/1/2026 Corrections Issued JESUS PINEDA
Green Building Final 5/1/2026 Approved JESUS PINEDA
HVAC-Final 5/1/2026 Approved JESUS PINEDA
PLUMBING-Final 5/1/2026 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 5/1/2026 SGSOV Approved JESUS PINEDA
Service/Power Release 5/1/2026 Approved JESUS PINEDA
Smoke Detectors 5/1/2026 Approved JESUS PINEDA