3601 N VERDUGO ROAD 90065

Certificate Information: 3601 N VERDUGO ROAD 90065

Application / Permit
25016-10000-10084
Plan Check / Job No.
B25LA12963
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan - MAJOR REMODEL TO EXSITING SFD "COMPLY WITH DEPARTMENT ORDER effective date 07/03/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE CEIS Case Number is 1011778.
Permit Issued
Issued on 5/1/2025
Issuing Office
Current Status
Issued on 5/1/2025

Permit Application Status History

Submitted 4/3/2025 APPLICANT
Assigned to Plan Check Engineer 4/10/2025 STARR CHEN
Plan Check Approved 4/30/2025 STARR CHEN
Issued 5/1/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/23/2025 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/20/2025 Corrections Issued FERMIN RUBIO
Pre-Inspection 6/24/2025 Not Ready for Inspection FERMIN RUBIO
Footing/Foundation/Slab 6/26/2025 Approved FERMIN RUBIO
BUILDING-Rough-Frame 7/2/2025 Not Ready for Inspection FERMIN RUBIO
ELECTRICAL-Rough 7/2/2025 Conditional Approval FERMIN RUBIO
PLUMBING-Rough 7/2/2025 Not Ready for Inspection FERMIN RUBIO
BUILDING-Rough-Frame 7/9/2025 Corrections Issued FERMIN RUBIO
ELECTRICAL-Rough 7/9/2025 Conditional Approval FERMIN RUBIO
MERV13>=Rough 7/9/2025 Conditional Approval FERMIN RUBIO
PLUMBING-Rough 7/9/2025 Conditional Approval FERMIN RUBIO
Insulation 7/31/2025 Approved FERMIN RUBIO
Deputy Wood Construction 8/27/2025 Conditional Approval FERMIN RUBIO
BUILDING-Rough-Frame 9/18/2025 Approved FERMIN RUBIO
ELECTRICAL-Rough 9/18/2025 Approved FERMIN RUBIO
Floor/Roof Diaphrgm/Shear Wall 9/18/2025 Approved FERMIN RUBIO
Footing/Foundation/Slab 9/18/2025 Approved FERMIN RUBIO
MERV13>=Rough 9/18/2025 Approved FERMIN RUBIO
PLUMBING-Rough 9/18/2025 Approved FERMIN RUBIO
Interior/Exterior Lathing 9/25/2025 Partial Approval FERMIN RUBIO
Drywall Nailing 10/1/2025 Not Ready for Inspection FERMIN RUBIO
Interior/Exterior Lathing 10/1/2025 Approved FERMIN RUBIO