8110 W BEVERLY BLVD 90048
Certificate Information: 8110 W BEVERLY BLVD 90048
- Application / Permit
- 25016-10000-10038
- Plan Check / Job No.
- B25LA12874
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Gymnasium
- Work Description
- CHANGE OF USE FROM RETAIL TO FITNESS GYM
- Permit Issued
- Issued on 6/30/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2025 | APPLICANT |
| Assigned to Zoning Architect | 4/3/2025 | HAYDON CHAN |
| Assigned to Plan Check Engineer | 4/10/2025 | HERNAN ARREOLA |
| Corrections Issued | 4/21/2025 | HERNAN ARREOLA |
| Quality Review Completed | 4/23/2025 | KEN GILL |
| Building Plans Picked Up | 4/30/2025 | APPLICANT |
| Disabled Access Plans Picked Up | 5/2/2025 | APPLICANT |
| Plan Check Approved | 6/26/2025 | CAROLYNN NEPOMUCENO |
| No Progress | 6/26/2025 | CAROLYNN NEPOMUCENO |
| Plan Check Approved | 6/27/2025 | HERNAN ARREOLA |
| Issued | 6/30/2025 | APPLICANT |
| CofO in Progress | 10/27/2025 | MARTIN TAVITIAN |
| Permit Finaled | 11/7/2025 | ERNESTO CORRAL |
| CofO Issued | 11/7/2025 | ERNESTO CORRAL |
| Permit Finaled | 11/7/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| ZI | Cleared | 4/16/2025 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 5/6/2025 | JESSICA OPINION |
| Green Code | Cleared | 6/4/2025 | HERNAN ARREOLA |
| DAS Clearance | Cleared | 6/6/2025 | HERNAN ARREOLA |
| Zoning Plan Check | Cleared | 6/10/2025 | HERNAN ARREOLA |
Contact Information
| Architect | Thomas,, Leslie; Lic. No.: C26651 | 1074 W TAYLOR STREET #113 CHICAGO, IL 60607 |
| Contractor | Pacific Construction Partners Llc; Lic. No.: 1106225-B | 1608 PACIFIC AVE VENICE, CA 90291 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 7/22/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 8/13/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Green Building Final | 8/13/2025 | Approved | MARTIN TAVITIAN |
| METHANE-Final | 8/13/2025 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 8/13/2025 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 8/13/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Light Gage Steel Frame | 8/15/2025 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 8/19/2025 | Approved | MARTIN TAVITIAN |
| Final | 9/3/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Smoke Detectors | 9/3/2025 | Approved | MARTIN TAVITIAN |
| Final | 9/15/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 9/26/2025 | OK to Issue CofO | MARTIN TAVITIAN |