3165 W LACLEDE AVE 90039
Certificate Information: 3165 W LACLEDE AVE 90039
- Application / Permit
- 25016-10000-09768
- Plan Check / Job No.
- B25LA12564
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. CONVERT EXISTING GARAGE TO ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/24/2025
- Issuing Office
- Current Status
- CofO Issued on 2/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2025 | DANIEL SANJUAN |
| Corrections Issued | 4/9/2025 | DANIEL SANJUAN |
| Plan Check Approved | 7/24/2025 | NEHEMIAS RAMOS |
| Issued | 7/24/2025 | APPLICANT |
| CofO in Progress | 2/17/2026 | NICHOLAS LOPEZ |
| Permit Finaled | 2/22/2026 | DEROLD HAUFF |
| Permit Finaled | 2/22/2026 | DEROLD HAUFF |
| CofO Issued | 2/22/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/12/2025 | JAZMIN ROQUE |
| ZI | Cleared | 4/12/2025 | JAZMIN ROQUE |
| Address approval | Cleared | 4/13/2025 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 4/18/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 4/18/2025 | JESSICA OPINION |
| Construction near power lines | Cleared | 7/21/2025 | EDGAR PASCUA |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2025 | JESSICA OPINION |
Contact Information
| Contractor | J V P Construction; Lic. No.: 811926-B | , |
| Engineer | Tsai,, Willy Y; Lic. No.: NA35589 | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/5/2025 | Conditional Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 8/5/2025 | Partial Approval | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 8/18/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 8/18/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| PLUMBING-Rough | 8/25/2025 | Partial Approval | NICHOLAS LOPEZ |
| Sewer | 8/25/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 10/1/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 10/1/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Rough | 10/1/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 10/1/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 10/10/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 10/10/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 10/10/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 10/17/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 10/30/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 10/30/2025 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 10/30/2025 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 11/19/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 12/26/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 12/26/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 12/26/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 12/26/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/26/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 12/26/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 1/16/2026 | Corrections Issued | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/16/2026 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 1/16/2026 | Approved | NICHOLAS LOPEZ |
| Final | 2/17/2026 | OK to Issue CofO | NICHOLAS LOPEZ |