3820 S MENTONE AVE 1-11 90232

Certificate Information: 3820 S MENTONE AVE 1-11 90232

Application / Permit
25016-10000-09548
Plan Check / Job No.
B25LA12367
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT THE (E) ATTACHED LAUNDRY ROOM (103.47 SQ.FT) AND PORTION OF ATTACHED GARAGE (273.04 SQ.FT) WITHIN THE (E) APARTMENT BUIDLING INTO AN ACCESSORY DWELLING UNIT (UNIT #11) PER GC 66323(a)(3).
Permit Issued
Issued on 9/19/2025
Issuing Office
Current Status
CofO Issued on 5/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2025 APPLICANT
Assigned to Plan Check Engineer 4/4/2025 ROSENDO MEDINA
Corrections Issued 4/9/2025 ROSENDO MEDINA
Plan Check Approved 5/29/2025 SARKIS HARABEDIAN
Issued 9/19/2025 APPLICANT
CofO in Progress 5/12/2026 FARHAD DADBIN
Permit Finaled 5/12/2026 VASIL MIHALEV
CofO Issued 5/12/2026 VASIL MIHALEV
Permit Finaled 5/12/2026 VASIL MIHALEV

Permit Application Clearance Information

Address approval Cleared 4/23/2025 RYAN CASTRO
Sewer availability Cleared 4/23/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/28/2025 RYAN CASTRO
Tenant Habitability Plan Cleared 4/29/2025 KORNEL LELEA

Contact Information

Contractor Guevara Josue E; Lic. No.: 1018358-B       ,
Contractor Josue E Guevara; Lic. No.: 1018358-B       ,
Engineer Gao,, Jianfeng; Lic. No.: C88478 18825 ELMHURST ST      ROWLAND HEIGHTS, CA 91748

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/1/2025 Not Ready for Inspection FARHAD DADBIN
Footing/Foundation/Slab 11/7/2025 Approved FARHAD DADBIN
Footing/Foundation/Slab 1/20/2026 Approved FARHAD DADBIN
Green Building Rough 1/20/2026 Approved FARHAD DADBIN
METHANE-Rough 1/20/2026 Approved FARHAD DADBIN
Wood Frame 1/20/2026 Partial Approval FARHAD DADBIN
Footing/Foundation/Slab 1/27/2026 Partial Approval FARHAD DADBIN
Pre-Inspection 1/27/2026 Partial Approval FARHAD DADBIN
Pre-Inspection 2/18/2026 Conditional Approval FARHAD DADBIN
Drywall Nailing 2/24/2026 Approved FARHAD DADBIN
Interior/Exterior Lathing 3/16/2026 Approved PAUL DAVIDSON
Final 4/23/2026 Not Ready for Inspection FARHAD DADBIN
Green Building Final 4/23/2026 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 4/23/2026 SGSOV Approved FARHAD DADBIN
Smoke Detectors 4/23/2026 Approved FARHAD DADBIN
Wood Frame 4/23/2026 Approved FARHAD DADBIN
Final 5/12/2026 OK to Issue CofO FARHAD DADBIN