3820 S MENTONE AVE 1-11 90232
Certificate Information: 3820 S MENTONE AVE 1-11 90232
- Application / Permit
- 25016-10000-09548
- Plan Check / Job No.
- B25LA12367
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT THE (E) ATTACHED LAUNDRY ROOM (103.47 SQ.FT) AND PORTION OF ATTACHED GARAGE (273.04 SQ.FT) WITHIN THE (E) APARTMENT BUIDLING INTO AN ACCESSORY DWELLING UNIT (UNIT #11) PER GC 66323(a)(3).
- Permit Issued
- Issued on 9/19/2025
- Issuing Office
- Current Status
- CofO Issued on 5/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2025 | ROSENDO MEDINA |
| Corrections Issued | 4/9/2025 | ROSENDO MEDINA |
| Plan Check Approved | 5/29/2025 | SARKIS HARABEDIAN |
| Issued | 9/19/2025 | APPLICANT |
| CofO in Progress | 5/12/2026 | FARHAD DADBIN |
| Permit Finaled | 5/12/2026 | VASIL MIHALEV |
| CofO Issued | 5/12/2026 | VASIL MIHALEV |
| Permit Finaled | 5/12/2026 | VASIL MIHALEV |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 4/23/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2025 | RYAN CASTRO |
| Tenant Habitability Plan | Cleared | 4/29/2025 | KORNEL LELEA |
Contact Information
| Contractor | Guevara Josue E; Lic. No.: 1018358-B | , |
| Contractor | Josue E Guevara; Lic. No.: 1018358-B | , |
| Engineer | Gao,, Jianfeng; Lic. No.: C88478 | 18825 ELMHURST ST ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/1/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 11/7/2025 | Approved | FARHAD DADBIN |
| Footing/Foundation/Slab | 1/20/2026 | Approved | FARHAD DADBIN |
| Green Building Rough | 1/20/2026 | Approved | FARHAD DADBIN |
| METHANE-Rough | 1/20/2026 | Approved | FARHAD DADBIN |
| Wood Frame | 1/20/2026 | Partial Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 1/27/2026 | Partial Approval | FARHAD DADBIN |
| Pre-Inspection | 1/27/2026 | Partial Approval | FARHAD DADBIN |
| Pre-Inspection | 2/18/2026 | Conditional Approval | FARHAD DADBIN |
| Drywall Nailing | 2/24/2026 | Approved | FARHAD DADBIN |
| Interior/Exterior Lathing | 3/16/2026 | Approved | PAUL DAVIDSON |
| Final | 4/23/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 4/23/2026 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 4/23/2026 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 4/23/2026 | Approved | FARHAD DADBIN |
| Wood Frame | 4/23/2026 | Approved | FARHAD DADBIN |
| Final | 5/12/2026 | OK to Issue CofO | FARHAD DADBIN |