4444 N CEDROS AVE 91403
Certificate Information: 4444 N CEDROS AVE 91403
- Application / Permit
- 25016-10000-09438
- Plan Check / Job No.
- B25LA12348
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan REMOVING WALL IN THE KITECHN ADD BATHROOM AND CLOEST TO THE BEDROOM TO MAKE A MASTER BEDROOM
- Permit Issued
- Issued on 4/14/2025
- Issuing Office
- Current Status
- Permit Finaled on 8/7/2025
Permit Application Status History
| Submitted | 3/31/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2025 | JOHN MESIAS |
| Corrections Issued | 4/5/2025 | JOHN MESIAS |
| Plan Check Approved | 4/14/2025 | JOHN MESIAS |
| Issued | 4/14/2025 | APPLICANT |
| Permit Finaled | 8/6/2025 | MISAEL ESPARZA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | California Kitchen Gallery; Lic. No.: 991830-B | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/25/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/2/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/2/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/5/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/5/2025 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/5/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 5/5/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/8/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 5/8/2025 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/8/2025 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/8/2025 | Approved | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 5/12/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/14/2025 | Partial Inspection | JOSE AVILA |
| Final | 8/6/2025 | Permit Finaled | MISAEL ESPARZA |
| Smoke Detectors | 8/6/2025 | Approved | MISAEL ESPARZA |