2250-2250 1/2 E GATEWOOD ST 90031
Certificate Information: 2250-2250 1/2 E GATEWOOD ST 90031
- Application / Permit
- 25016-10000-09410
- Plan Check / Job No.
- B25LA12322
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT (E) DETACHED 4-CAR GARAGE INTO 2 (N) ACCESSORY DWELLING UNITS PER GCS 66323(a)(4). NFPA-13D FIRE SPRINKLER SYSTEM THROUGHOUT.
- Permit Issued
- Issued on 7/25/2025
- Issuing Office
- Current Status
- CofO Issued on 3/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2025 | ISIS ARGUETA |
| Corrections Issued | 4/9/2025 | ISIS ARGUETA |
| Applicant returned to address corrections | 5/23/2025 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 6/4/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 6/25/2025 | NAREG ATARIAN |
| Plan Check Approved | 7/24/2025 | ISIS ARGUETA |
| Issued | 7/25/2025 | APPLICANT |
| CofO in Progress | 3/19/2026 | HAMIK HARTOUNIAN |
| Permit Finaled | 3/19/2026 | DEROLD HAUFF |
| CofO Issued | 3/19/2026 | DEROLD HAUFF |
| Permit Finaled | 3/19/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 4/22/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2025 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 6/20/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/13/2025 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 8/13/2025 | Partial Approval | BRENDAN MORELLI |
| Deputy Drilled-In Anchors | 8/18/2025 | Conditional Approval | ALEX COLIN |
| Footing/Foundation/Slab | 8/19/2025 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/13/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 11/13/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 11/18/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/18/2025 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 11/18/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 11/21/2025 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 11/21/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 11/26/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/26/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 12/4/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 12/4/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 2/12/2026 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 2/12/2026 | Corrections Issued | WILLIAM SIERRA |
| Final | 2/12/2026 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 2/12/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| Green Building Rough | 2/12/2026 | Approved | WILLIAM SIERRA |
| MERV13>=Final | 2/12/2026 | Corrections Issued | WILLIAM SIERRA |
| MERV13>=Rough | 2/12/2026 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 2/12/2026 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 2/12/2026 | SGSOV Not Ready | WILLIAM SIERRA |
| Smoke Detectors | 2/12/2026 | Approved | WILLIAM SIERRA |
| Special/Order Compliance | 2/12/2026 | Partial Inspection | OSVALDO PARAMO |
| Final | 2/20/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 2/20/2026 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 2/20/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/20/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Sewer | 3/6/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 3/18/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Service/Power Release | 3/18/2026 | Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 3/18/2026 | Partial Inspection | OSVALDO PARAMO |