5312 E LINCOLN AVE 90042

Certificate Information: 5312 E LINCOLN AVE 90042

Application / Permit
25016-10000-09369
Plan Check / Job No.
B25LA12276
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING DETACHED GARAGE TO BE CONVERTED TO A DETACHED ADU PER GC 66323(a)(1)
Permit Issued
Issued on 6/3/2025
Issuing Office
Current Status
CofO Issued on 1/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2025 APPLICANT
Assigned to Plan Check Engineer 4/4/2025 SUNMIN LEE
Corrections Issued 4/7/2025 SUNMIN LEE
Plan Check Approved 5/3/2025 CARLOS MONTES
Issued 6/3/2025 APPLICANT
CofO in Progress 1/13/2026 DAVID WILLIAMS
Permit Finaled 1/14/2026 DEROLD HAUFF
Permit Finaled 1/14/2026 DEROLD HAUFF
CofO Issued 1/14/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/12/2025 TREVOR QUAN
Roof/Waste drainage to street Cleared 4/12/2025 TREVOR QUAN
Sewer availability Cleared 4/12/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 4/15/2025 TREVOR QUAN
Grading Pre-Inspection Cleared 4/21/2025 JONATHAN HOM

Contact Information

Contractor Construction By Maya Inc; Lic. No.: 1034501-B       ,
Engineer Kashe,, Andrew; Lic. No.: NA94117       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/10/2025 Conditional Approval REGINA MENDEZ
Footing/Foundation/Slab 6/12/2025 Approved DAVID WILLIAMS
Underground Mechanical 6/16/2025 Not Ready for Inspection DAVID WILLIAMS
Sewer 6/18/2025 Corrections Issued LILIANA PORTILLO
Special/Order Compliance 6/18/2025 Partial Inspection CHARLES BOGHOSKHAN
Underground Mechanical 6/18/2025 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 7/1/2025 Partial Approval DAVID WILLIAMS
Rough-Elec/Plmb/HVAC 7/1/2025 Approved DAVID WILLIAMS
Shower Pan 7/1/2025 Approved DAVID WILLIAMS
Wood Frame 7/1/2025 Approved DAVID WILLIAMS
Insulation 7/9/2025 Corrections Issued GEM DE OCAMPO
Interior/Exterior Lathing 7/9/2025 Approved GEM DE OCAMPO
Insulation 7/10/2025 Approved GEM DE OCAMPO
Interior/Exterior Lathing 7/11/2025 Approved DAVID WILLIAMS
Drywall Nailing 7/14/2025 Approved REGINA MENDEZ
Pre-Inspection 11/13/2025 Partial Approval DAVID WILLIAMS
PLUMBING-Final 12/15/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 1/9/2026 Approved DAVID WILLIAMS
ELECTRICAL-Final 1/9/2026 Approved DAVID WILLIAMS
Final 1/9/2026 Corrections Issued DAVID WILLIAMS
Green Building Final 1/9/2026 Approved DAVID WILLIAMS
Green Building Rough 1/9/2026 Approved DAVID WILLIAMS
HVAC-Final 1/9/2026 Approved DAVID WILLIAMS
PLUMBING-Final 1/9/2026 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 1/9/2026 SGSOV No Gas DAVID WILLIAMS
Smoke Detectors 1/9/2026 Approved DAVID WILLIAMS
Final 1/13/2026 OK to Issue CofO DAVID WILLIAMS