555 S FLOWER ST 22nd FL 90071

Certificate Information: 555 S FLOWER ST 22nd FL 90071

Application / Permit
25016-10000-09253
Plan Check / Job No.
B25LA12104
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
(ePLAN) Tenant improvement to convert office area into a covered patio at 22nd floor. Work per engineer details.
Permit Issued
Issued on 9/30/2025
Issuing Office
Current Status
Issued on 9/30/2025

Permit Application Status History

Submitted 3/28/2025 APPLICANT
Assigned to Plan Check Engineer 4/3/2025 VICTOR CHEN
Assigned to Zoning Architect 4/3/2025 NEVRIK NAVASARTIAN
Corrections Issued 4/7/2025 VICTOR CHEN
Quality Review Completed 4/9/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/26/2025 VICTOR CHEN
Plan Check Approved 9/22/2025 VICTOR CHEN
Issued 9/30/2025 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 4/23/2025 DALIA MOKAYED
Miscellaneous Cleared 4/23/2025 DALIA MOKAYED
Miscellaneous Cleared 4/23/2025 DALIA MOKAYED
ZA Case Cleared 5/5/2025 MATTHEW COMPANA
Green Code Cleared 5/15/2025 AARON COSTA
DAS Clearance Cleared 8/1/2025 ELIZABETH TOMS
Fire Marshal Fire Life Safety Cleared 8/17/2025 VICTOR CHEN
Zoning Plan Check Cleared 8/20/2025 NEVRIK NAVASARTIAN

Contact Information

Architect Kemp,, James A; Lic. No.: C37679 559 N MARENTO AVE #2      PASADENA, CA 91101
Contractor Bcci Construction Llc; Lic. No.: 492944-B       ,
Engineer Wilkerson,, Ryan Lee; Lic. No.: S4728 20734 SARDINIA WAY      PORTER RANCH, CA 91326

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 10/6/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 10/21/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 10/27/2025 Partial Approval PAUL BAZERKANIAN
Interior/Exterior Lathing 11/5/2025 Not Ready for Inspection PAUL BAZERKANIAN
Interior/Exterior Lathing 11/7/2025 Partial Approval PAUL BAZERKANIAN
Final 12/11/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Green Building Final 12/11/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Approved CHRISTOPHER BLACKWOOD
Smoke Detectors 12/11/2025 Approved CHRISTOPHER BLACKWOOD
Final 12/16/2025 Not Ready for Inspection PAUL BAZERKANIAN
Green Building Final 12/17/2025 Partial Approval PAUL BAZERKANIAN
Green Building Rough 12/17/2025 Partial Approval PAUL BAZERKANIAN