1177 S BEVERLY DR 90035

Certificate Information: 1177 S BEVERLY DR 90035

Application / Permit
25016-10000-09223
Plan Check / Job No.
B25LA12047
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
PROJECT CONSISTS OF: 1). CONVERSION OF EXISTING TWO BEDROOM SUITE ON FLOORS 2-8, INTO 2 STANDARD. QUEEN GUEST ROOMS FR A NET GAIN OF 7 ROOMS. 2). TOTAL GUEST ROOM COUNT INCREASED FROM 186 KEYS TO 193 KEYS. 3). ROOM #722 CONVERTED TO AN ACCESSIBLE QUEEN ROOM.
Permit Issued
Issued on 10/27/2025
Issuing Office
Metro
Current Status
Permit Finaled on 2/5/2026

Permit Application Status History

Submitted 3/27/2025 APPLICANT
Assigned to Plan Check Engineer 4/3/2025 ARSALAN SHABESTARI
Assigned to Zoning Architect 4/3/2025 FRANCIS AHN
Corrections Issued 4/10/2025 ARSALAN SHABESTARI
Quality Review Completed 4/14/2025 KEN GILL
Building Plans Picked Up 4/15/2025 APPLICANT
Plan Check Approved 8/20/2025 ARSALAN SHABESTARI
Issued 10/27/2025 APPLICANT
Permit Finaled 2/2/2026 FARHAD DADBIN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/15/2025 COLIN LOREDO
Sewer availability Cleared 4/15/2025 COLIN LOREDO
Fire Marshal Fire Life Safety Cleared 5/2/2025 FIRE DEPARTMENT
Miscellaneous Cleared 5/21/2025 DALIA MOKAYED
Miscellaneous Cleared 5/22/2025 DALIA MOKAYED
Miscellaneous Cleared 7/3/2025 JACQUELINE TORRES
Miscellaneous Cleared 7/8/2025 RICARDO MARTINEZ
Miscellaneous Cleared 7/8/2025 RICARDO MARTINEZ
DAS Clearance Cleared 7/23/2025 ARSALAN SHABESTARI
Zoning Plan Check Cleared 7/23/2025 ARSALAN SHABESTARI

Contact Information

Contractor Olson R D Construction Inc; Lic. No.: 953845-B 400 SPECTRUM CENTER DR   STE 1200    IRVINE, CA 92618

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/13/2025 Approved FARHAD DADBIN
Light Gage Steel Frame 12/9/2025 Not Ready for Inspection FARHAD DADBIN
Insulation 12/12/2025 Not Ready for Inspection FARHAD DADBIN
Light Gage Steel Frame 12/12/2025 Not Ready for Inspection FARHAD DADBIN
Insulation 12/16/2025 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 12/16/2025 Partial Approval FARHAD DADBIN
Drywall Nailing 12/18/2025 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 1/9/2026 Partial Approval FARHAD DADBIN
Drywall Nailing 1/15/2026 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 1/15/2026 Partial Approval FARHAD DADBIN
Drywall Nailing 1/20/2026 Approved FARHAD DADBIN
Light Gage Steel Frame 1/20/2026 Approved FARHAD DADBIN
Final 2/2/2026 Permit Finaled FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 2/2/2026 SGSOV Approved FARHAD DADBIN
Smoke Detectors 2/2/2026 Approved FARHAD DADBIN