1722 W 260TH ST 90717
Certificate Information: 1722 W 260TH ST 90717
- Application / Permit
- 25016-10000-08741
- Plan Check / Job No.
- B25LA11459
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert (E) Detached Garage to Accessory Dwelling Unit per state law
- Permit Issued
- Issued on 4/30/2025
- Issuing Office
- Current Status
- CofO Issued on 4/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2025 | NGHI SU |
| Corrections Issued | 3/26/2025 | NGHI SU |
| Applicant returned to address corrections | 4/11/2025 | NGHI SU |
| Plan Check Approved | 4/29/2025 | NGHI SU |
| Issued | 4/30/2025 | APPLICANT |
| CofO in Progress | 4/23/2026 | BEN MOLSTAD |
| Permit Finaled | 4/23/2026 | ANSON MAGLASANG |
| CofO Issued | 4/23/2026 | ANSON MAGLASANG |
| Permit Finaled | 4/23/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 4/9/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 4/9/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 4/10/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/30/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/10/2025 | Approved | EUGENE CASSIDY |
| Pre-Inspection | 10/10/2025 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/22/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/22/2025 | Approved | EUGENE CASSIDY |
| Gas Test | 10/22/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 10/22/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/22/2025 | Approved | EUGENE CASSIDY |
| Sewer | 10/22/2025 | Approved | EUGENE CASSIDY |
| Insulation | 11/10/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/10/2025 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 12/12/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/12/2025 | Approved | EUGENE CASSIDY |
| Final | 3/6/2026 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 3/6/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Pre-Inspection | 3/6/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 3/6/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 4/15/2026 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/15/2026 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/15/2026 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 4/15/2026 | Approved | EUGENE CASSIDY |
| Final | 4/20/2026 | OK to Issue CofO | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/20/2026 | SGSOV Approved | BEN MOLSTAD |
| Service/Power Release | 4/22/2026 | Approved | EUGENE CASSIDY |