2526 S FEDERAL AVE 90064

Certificate Information: 2526 S FEDERAL AVE 90064

Application / Permit
25016-10000-08728
Plan Check / Job No.
B25LA11424
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert existing detached garage into ADU per GC 66323(a)(1). All work per WFPP.
Permit Issued
Issued on 5/3/2025
Issuing Office
Current Status
CofO Issued on 2/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2025 APPLICANT
Assigned to Plan Check Engineer 3/28/2025 DAVID CASTILLO
Corrections Issued 3/30/2025 DAVID CASTILLO
Applicant returned to address corrections 4/24/2025 DAVID CASTILLO
Plan Check Approved 5/2/2025 DAVID CASTILLO
Issued 5/3/2025 APPLICANT
CofO in Progress 2/13/2026 ARAM AVEDISIAN
Permit Finaled 2/20/2026 RICHARD STEINBACH
CofO Issued 2/20/2026 RICHARD STEINBACH
Permit Finaled 2/20/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/2/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/2/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 4/2/2025 RYAN CASTRO
Sewer availability Cleared 4/2/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/17/2025 Partial Approval WILBER ROSALES
Sewer 6/25/2025 Partial Approval WILBER ROSALES
Underground Mechanical 6/25/2025 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/1/2025 Partial Approval WILBER ROSALES
Underground Mechanical 7/1/2025 Partial Approval WILBER ROSALES
Interior/Exterior Lathing 7/9/2025 Not Ready for Inspection JAYLIN GRAVITTE
Interior/Exterior Lathing 7/10/2025 Partial Approval WILBER ROSALES
ELECTRICAL-Rough 7/22/2025 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 7/31/2025 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 7/31/2025 Corrections Issued BOBBY KEY
Wood Frame 7/31/2025 Not Ready for Inspection BOBBY KEY
Gas Test 8/14/2025 No Access for Inspection KIRK SANDERS
PLUMBING-Rough 8/14/2025 No Access for Inspection KIRK SANDERS
Footing/Foundation/Slab 8/18/2025 Not Ready for Inspection KIRK SANDERS
Gas Test 8/18/2025 Corrections Issued KIRK SANDERS
HVAC-Rough 8/18/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 8/18/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 8/20/2025 No Access for Inspection KIRK SANDERS
Gas Test 8/22/2025 Corrections Issued JAYLIN GRAVITTE
BUILDING-Rough-Frame 8/25/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 8/25/2025 Approved ARAM AVEDISIAN
Green Building Rough 8/25/2025 Approved ARAM AVEDISIAN
HVAC-Rough 8/25/2025 Approved ARAM AVEDISIAN
MERV13>=Rough 8/25/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 8/25/2025 Partial Approval ARAM AVEDISIAN
Insulation 8/28/2025 Corrections Issued KIRK SANDERS
Insulation 9/4/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 9/10/2025 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 9/10/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 9/12/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Approved KIRK SANDERS
Drywall Nailing 9/18/2025 No Access for Inspection KIRK SANDERS
Drywall Nailing 9/19/2025 Not Ready for Inspection KIRK SANDERS
Drywall Nailing 9/23/2025 Approved CARLOS MATAMOROS
Underground Mechanical 9/23/2025 Approved CARLOS MATAMOROS
Shower Pan 10/14/2025 No Access for Inspection ROBERT CORNELL
Shower Pan 10/16/2025 Corrections Issued JESUS RODRIGUEZ
Shower Pan 10/21/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 11/14/2025 Approved KIRK SANDERS
Final 2/6/2026 Corrections Issued ARAM AVEDISIAN
Green Building Final 2/6/2026 Not Ready for Inspection ARAM AVEDISIAN
MERV13>=Final 2/6/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 2/6/2026 Approved ARAM AVEDISIAN
ELECTRICAL-Final 2/13/2026 Approved ARAM AVEDISIAN
Final 2/13/2026 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 2/13/2026 Approved ARAM AVEDISIAN
HVAC-Final 2/13/2026 Approved ARAM AVEDISIAN
PLUMBING-Final 2/13/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Approved ARAM AVEDISIAN