3550 S GLENDON AVE 90034
Certificate Information: 3550 S GLENDON AVE 90034
- Application / Permit
- 25016-10000-08482
- Plan Check / Job No.
- B25LA11138
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED RECREATION ROOM TO NEW ACCESSORY DWELLING UNIT PER GCS 66323(e)(1)(A). EXISTING CARPORT ATTACHED TO REMAIN. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 6/2/2025
- Issuing Office
- Current Status
- CofO Issued on 3/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | MADISON ODELL |
| Corrections Issued | 3/27/2025 | MADISON ODELL |
| Applicant returned to address corrections | 5/2/2025 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 5/14/2025 | MADISON ODELL |
| Plan Check Approved | 5/27/2025 | MADISON O'DELL |
| Issued | 6/2/2025 | APPLICANT |
| CofO in Progress | 3/13/2026 | ARAM AVEDISIAN |
| Permit Finaled | 3/16/2026 | RICHARD STEINBACH |
| CofO Issued | 3/16/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/16/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/29/2025 | DARIN LAM |
| Sewer availability | Cleared | 3/29/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2025 | DARIN LAM |
| Specific Plan | Cleared | 4/29/2025 | JOSHUA JONES |
| Grading Pre-Inspection | Cleared | 5/7/2025 | LANNY MERRICK |
Contact Information
| Contractor | Vigorous W Construction Llc; Lic. No.: 1108724-B | 17114 RIDGE PARK DR HACIENDA HEIGHTS, CA 91745 |
| Engineer | Gao,, Jianfeng; Lic. No.: C88478 | 18825 ELMHURST ST ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/31/2025 | Approved | MICHAEL ALLEN |
| Gas Test | 7/31/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 7/31/2025 | Approved | MICHAEL ALLEN |
| Sewer | 7/31/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 8/12/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Wood Frame | 8/12/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 8/15/2025 | Corrections Issued | EVAN COOPER |
| Gas Test | 8/15/2025 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 8/15/2025 | Approved | EVAN COOPER |
| Smoke Detectors | 8/15/2025 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 8/21/2025 | Corrections Issued | STEPHANIE SWANSON |
| Rough-Elec/Plmb/HVAC | 8/21/2025 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/27/2025 | Not Ready for Inspection | JAYLIN GRAVITTE |
| Green Building Rough | 8/27/2025 | Approved | JAYLIN GRAVITTE |
| Insulation | 8/27/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 8/27/2025 | Partial Approval | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | KIRK SANDERS |
| Drywall Nailing | 9/3/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 9/3/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 9/3/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Shower Pan | 9/4/2025 | Approved | KIRK SANDERS |
| Final | 11/10/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 11/10/2025 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/10/2025 | SGSOV Not Ready | KIRK SANDERS |
| Service/Power Release | 11/10/2025 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 11/10/2025 | Approved | KIRK SANDERS |
| Final | 3/6/2026 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 3/6/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Not Ready | ARAM AVEDISIAN |
| Service/Power Release | 3/6/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 3/13/2026 | OK to Issue CofO | ARAM AVEDISIAN |
| Final | 3/13/2026 | Partial Approval | ARAM AVEDISIAN |
| Green Building Final | 3/13/2026 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 3/13/2026 | Approved | ARAM AVEDISIAN |
| Service/Power Release | 3/13/2026 | Not Ready for Inspection | ARAM AVEDISIAN |