3550 S GLENDON AVE 90034

Certificate Information: 3550 S GLENDON AVE 90034

Application / Permit
25016-10000-08482
Plan Check / Job No.
B25LA11138
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED RECREATION ROOM TO NEW ACCESSORY DWELLING UNIT PER GCS 66323(e)(1)(A). EXISTING CARPORT ATTACHED TO REMAIN. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 6/2/2025
Issuing Office
Current Status
CofO Issued on 3/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2025 APPLICANT
Assigned to Plan Check Engineer 3/27/2025 MADISON ODELL
Corrections Issued 3/27/2025 MADISON ODELL
Applicant returned to address corrections 5/2/2025 SARKIS HARABEDIAN
Applicant returned to address corrections 5/14/2025 MADISON ODELL
Plan Check Approved 5/27/2025 MADISON O'DELL
Issued 6/2/2025 APPLICANT
CofO in Progress 3/13/2026 ARAM AVEDISIAN
Permit Finaled 3/16/2026 RICHARD STEINBACH
CofO Issued 3/16/2026 RICHARD STEINBACH
Permit Finaled 3/16/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/29/2025 DARIN LAM
Sewer availability Cleared 3/29/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 4/2/2025 DARIN LAM
Specific Plan Cleared 4/29/2025 JOSHUA JONES
Grading Pre-Inspection Cleared 5/7/2025 LANNY MERRICK

Contact Information

Contractor Vigorous W Construction Llc; Lic. No.: 1108724-B 17114 RIDGE PARK DR      HACIENDA HEIGHTS, CA 91745
Engineer Gao,, Jianfeng; Lic. No.: C88478 18825 ELMHURST ST      ROWLAND HEIGHTS, CA 91748

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/31/2025 Approved MICHAEL ALLEN
Gas Test 7/31/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 7/31/2025 Approved MICHAEL ALLEN
Sewer 7/31/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 8/12/2025 Corrections Issued TEMISTOCLES CAAL
Wood Frame 8/12/2025 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Rough 8/15/2025 Corrections Issued EVAN COOPER
Gas Test 8/15/2025 Partial Approval EVAN COOPER
HVAC-Rough 8/15/2025 Approved EVAN COOPER
Smoke Detectors 8/15/2025 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 8/21/2025 Corrections Issued STEPHANIE SWANSON
Rough-Elec/Plmb/HVAC 8/21/2025 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 8/27/2025 Not Ready for Inspection JAYLIN GRAVITTE
Green Building Rough 8/27/2025 Approved JAYLIN GRAVITTE
Insulation 8/27/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 8/27/2025 Partial Approval JAYLIN GRAVITTE
BUILDING-Rough-Frame 8/29/2025 Approved KIRK SANDERS
Drywall Nailing 9/3/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 9/3/2025 Approved JAYLIN GRAVITTE
Shower Pan 9/3/2025 Corrections Issued JAYLIN GRAVITTE
Shower Pan 9/4/2025 Approved KIRK SANDERS
Final 11/10/2025 Corrections Issued KIRK SANDERS
Green Building Final 11/10/2025 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Not Ready KIRK SANDERS
Service/Power Release 11/10/2025 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 11/10/2025 Approved KIRK SANDERS
Final 3/6/2026 Corrections Issued ARAM AVEDISIAN
Green Building Final 3/6/2026 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/6/2026 SGSOV Not Ready ARAM AVEDISIAN
Service/Power Release 3/6/2026 Not Ready for Inspection ARAM AVEDISIAN
Final 3/13/2026 OK to Issue CofO ARAM AVEDISIAN
Final 3/13/2026 Partial Approval ARAM AVEDISIAN
Green Building Final 3/13/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 3/13/2026 Approved ARAM AVEDISIAN
Service/Power Release 3/13/2026 Not Ready for Inspection ARAM AVEDISIAN