12437 W VENTURA BLVD 91604

Certificate Information: 12437 W VENTURA BLVD 91604

Application / Permit
25016-10000-08478
Plan Check / Job No.
B25LA11135
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Coffee Shop
Work Description
(ePLAN) Change of use from existing retail to coffee shop. REPLACING EXISTING STOREFRONT WINDOWS WITH NEW FULL HEIGHT WINDOWS . STRUCTURAL WORK TO INCLUDE REMOVING 3- EXISTING SUPPORT COLUMNS AND REPLACING THEM WITH 4 NEW POSTS SUPPORTING NEW BEAMS FROM THE FRONT OF THE BUILDING TO THE BACK. NO CHANGE IN SQUARE FOOTAGE, PARKING,
Permit Issued
Issued on 7/17/2025
Issuing Office
Current Status
Issued on 7/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/24/2025 APPLICANT
Assigned to Plan Check Engineer 3/27/2025 VICTOR CHEN
Assigned to Zoning Architect 3/27/2025 NICOLE SALEEBA
Corrections Issued 4/1/2025 VICTOR CHEN
Quality Review Completed 4/10/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/27/2025 VICTOR CHEN
Plan Check Approved 7/3/2025 FARSHAD ALIMOHAMADI
Issued 7/17/2025 APPLICANT

Permit Application Clearance Information

Public Works-Highway Ded. Cleared 4/26/2025 LEE GUILBEAUX
Encroachment in public way Cleared 4/28/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/29/2025 RYAN CASTRO
Sewer availability Cleared 4/29/2025 RYAN CASTRO
Specific Plan Cleared 5/1/2025 ABRAHAM LAMONTAGNE
Miscellaneous Cleared 5/27/2025 ALEX VELA
Miscellaneous Cleared 5/27/2025 ALEX VELA
ZI Cleared 5/27/2025 ALEX VELA
Food Service Establishment Cleared 6/25/2025 CRYSTOL BRANDT
DAS Clearance Cleared 6/26/2025 Samuel Gonzalez
Zoning Plan Check Cleared 6/27/2025 NICOLE SALEEBA
Food establishment approval Cleared 7/3/2025 LACDHS APPROVED

Contact Information

Contractor Anointed Amir Construction; Lic. No.: 886584-B       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/6/2025 Partial Approval KENNETH ROBERTS
Excavation/Setback/Form/Re-Bar 9/22/2025 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 9/22/2025 Partial Approval JOHN KITCKO
Pre-Inspection 9/22/2025 Partial Approval JOHN KITCKO
Structural Steel Frame 9/22/2025 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 9/30/2025 Approved KENNETH ROBERTS
Structural Steel Frame 9/30/2025 Approved KENNETH ROBERTS
Wood Frame 9/30/2025 Not Ready for Inspection KENNETH ROBERTS
Light Gage Steel Frame 11/12/2025 Approved KENNETH ROBERTS
Structural Steel Frame 11/12/2025 Approved KENNETH ROBERTS
Wood Frame 11/12/2025 Approved KENNETH ROBERTS
Insulation 11/17/2025 Approved DEANDRE HOFFMAN
Drywall Nailing 12/19/2025 Approved KENNETH ROBERTS
T-Bar Ceiling 4/1/2026 Not Ready for Inspection JEFFREY FULTON
Pre-Inspection 5/28/2026 Partial Inspection SEAN GRIFFITH
Final 7/22/2026 Corrections Issued JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 7/22/2026 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 7/22/2026 Approved JOHN KITCKO