17801-17803 W LANARK ST 91335

Certificate Information: 17801-17803 W LANARK ST 91335

Application / Permit
25016-10000-08421
Plan Check / Job No.
B25LA11087
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: REMODEL (E) SFD AND CONVERT (E) ATTACHED GARAGE TO NEW JUNIOR ACCESSORY DWELLING UNIT PER GC 66323(a)(1) and 66333. PER ENGINEER DESIGN.
Permit Issued
Issued on 4/11/2025
Issuing Office
Current Status
CofO Issued on 8/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2025 APPLICANT
Assigned to Plan Check Engineer 3/26/2025 MIROOSH KHACHATOORIAN
Corrections Issued 3/27/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 4/10/2025 MIROOSH KHACHATOORIAN
Issued 4/11/2025 APPLICANT
CofO in Progress 7/23/2025 JUAN ALVARADO
Permit Finaled 8/12/2025 JOHN JANSON
CofO Issued 8/12/2025 JOHN JANSON
Permit Finaled 8/12/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/3/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 4/3/2025 MICHAEL BROWN
Sewer availability Cleared 4/3/2025 MICHAEL BROWN

Contact Information

Contractor Owner-Builder       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/28/2025 Partial Approval JUAN ALVARADO
BUILDING-Rough-Frame 4/30/2025 Not Ready for Inspection JUAN ALVARADO
Deputy Drilled-In Anchors 4/30/2025 Approved JUAN ALVARADO
Footing/Foundation/Slab 4/30/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 5/6/2025 Conditional Approval JUAN ALVARADO
PLUMBING-Rough 5/13/2025 Corrections Issued JUAN ALVARADO
PLUMBING-Rough 5/14/2025 Partial Approval JUAN ALVARADO
ELECTRICAL-Rough 5/21/2025 Approved JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Partial Approval JUAN ALVARADO
Interior/Exterior Lathing 5/23/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 5/30/2025 Partial Approval JUAN ALVARADO
PLUMBING-Rough 5/30/2025 Approved JUAN ALVARADO
HVAC-Rough 6/5/2025 Corrections Issued JUAN ALVARADO
Insulation 6/5/2025 Corrections Issued JUAN ALVARADO
Shower Pan 6/5/2025 Approved JUAN ALVARADO
Drywall Nailing 6/10/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 6/10/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 7/14/2025 Approved JUAN ALVARADO
Final 7/14/2025 Corrections Issued JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 7/14/2025 SGSOV Not Ready JUAN ALVARADO
Smoke Detectors 7/14/2025 Approved JUAN ALVARADO
ELECTRICAL-Final 7/22/2025 Approved JUAN ALVARADO
Final 7/22/2025 OK to Issue CofO JUAN ALVARADO
HVAC-Final 7/22/2025 Approved JUAN ALVARADO
PLUMBING-Final 7/22/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV Approved JUAN ALVARADO
Service/Power Release 7/22/2025 Approved JUAN ALVARADO