645 N AVALON BLVD 90744
Certificate Information: 645 N AVALON BLVD 90744
- Application / Permit
- 25016-10000-08366
- Plan Check / Job No.
- B25LA11047
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Change of use portion of building to office from office/retail with structural retrofit of (E) URM. LIMIT THE HOURS OF OPERATION FROM 7am TO 11pm. (CERTIFICATE OF OCCUPANCY MUST REFLECT THE HOURS)
- Permit Issued
- Issued on 2/24/2026
- Issuing Office
- Current Status
- Issued on 2/24/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | ARMEN JIVALAGIAN |
| Assigned to Zoning Architect | 3/27/2025 | SARHAD GHEVANDIAN |
| Corrections Issued | 4/1/2025 | ARMEN JIVALAGIAN |
| Quality Review Completed | 4/15/2025 | PETER KIM |
| Applicant returned to address corrections | 10/9/2025 | ARMEN JIVALAGIAN |
| Plan Check Approved | 2/4/2026 | ARMEN JIVALAGIAN |
| Issued | 2/24/2026 | APPLICANT |
Permit Application Clearance Information
| "D" conditions | Cleared | 4/29/2025 | BRENNEN OBETO |
| "Q" conditions | Cleared | 4/29/2025 | BRENNEN OBETO |
| Clean Up Green Up | Cleared | 4/29/2025 | BRENNEN OBETO |
| Comm Cor/Mini-Mall | Cleared | 4/29/2025 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 5/12/2025 | JEREMY CHOK |
| DAS Clearance | Cleared | 7/8/2025 | Luke Gonzales |
| Zoning Plan Check | Cleared | 7/8/2025 | SARHAD GHEVANDIAN |
Contact Information
| Architect | Cataldo,, John G; Lic. No.: NA10457 | , |
| Contractor | Toneman Development Corp; Lic. No.: 648053-B | , |
| Engineer | Salahaldin,, Aws; Lic. No.: NA95446 | , |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/29/2026 | Approved | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 4/29/2026 | Approved | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 5/20/2026 | Approved | MICHAEL PETRUSKO |