1093 E SUPERBA AVE 90291
Certificate Information: 1093 E SUPERBA AVE 90291
- Application / Permit
- 25016-10000-07482
- Plan Check / Job No.
- B25LA10211
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO A.D.U. PER STATE LAW (GCS 66323(a)(1)). CONST. PER W.F.P.P.
- Permit Issued
- Issued on 5/15/2025
- Issuing Office
- Current Status
- Issued on 5/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2025 | LAWRENCE QUIRANTE |
| Corrections Issued | 3/21/2025 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 3/25/2025 | APPLICANT |
| Applicant returned to address corrections | 5/8/2025 | NGHI SU |
| Plan Check Approved | 5/15/2025 | SHANGQIN XIE |
| Issued | 5/15/2025 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 4/17/2025 | SANDRA SOH |
| Specific Plan | Cleared | 4/17/2025 | RICHARD WOO |
| Address approval | Cleared | 4/18/2025 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 4/18/2025 | VLADIMIR ARUTYUNYAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2025 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Ene Builders; Lic. No.: 1113906-B | 21434 WYANDOTTE STREET CANOGA PARK, CA 91303 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/4/2025 | Partial Approval | JESUS RODRIGUEZ |
| Sewer | 6/4/2025 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 6/4/2025 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 6/10/2025 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 6/10/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/20/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 8/20/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/20/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/28/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 8/28/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/28/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 9/9/2025 | Approved | JAYLIN GRAVITTE |
| Drywall Nailing | 9/16/2025 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 9/19/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/25/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 11/21/2025 | Corrections Issued | RUBEN RIVAS |
| Final | 11/21/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 11/21/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 11/21/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 11/21/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 11/21/2025 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 11/21/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 12/3/2025 | Corrections Issued | RUBEN RIVAS |
| Final | 12/3/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Final | 12/3/2025 | Approved | RUBEN RIVAS |