1653 E 95TH PL 90002

Certificate Information: 1653 E 95TH PL 90002

Application / Permit
25016-10000-07460
Plan Check / Job No.
B25LA10164
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. GARAGE CONVERSION INTO ADU (415 SQ. FT.) - NEW LIVING ROOM, KITCHEN, BEDROOM & BATH
Permit Issued
Issued on 8/7/2025
Issuing Office
Current Status
Issued on 8/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/19/2025 APPLICANT
Assigned to Plan Check Engineer 3/24/2025 NEHEMIAS RAMOS
Corrections Issued 3/25/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 5/7/2025 JOHN MESIAS
Applicant returned to address corrections 5/15/2025 SUNMIN LEE
Plan Check Approved 8/5/2025 SUNMIN LEE
Issued 8/7/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/25/2025 DAVID VO
Eng Process Fee Ord 176,300 Cleared 4/29/2025 DAVID VO
Grading Pre-Inspection Cleared 4/30/2025 ROBERT PINA
Sewer availability Cleared 5/1/2025 DAVID LOPEZ
Construction near power lines Cleared 7/30/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/30/2025 Corrections Issued KEITH EDGHILL
Excavation/Setback/Form/Re-Bar 10/15/2025 Corrections Issued KEITH EDGHILL
Deputy Drilled-In Anchors 12/9/2025 Approved KEITH EDGHILL
Wood Frame 12/9/2025 Approved KEITH EDGHILL
ELECTRICAL-Rough 1/6/2026 Approved KEITH EDGHILL
Sewer 1/9/2026 Approved KEITH EDGHILL
Insulation 1/16/2026 Approved KEITH EDGHILL
Drywall Nailing 1/23/2026 Approved KEITH EDGHILL
Non Compliance 2/20/2026 Refer to Special Investigation KEITH EDGHILL
BUILDING-Rough-Frame 3/12/2026 Approved KEITH EDGHILL
Final 3/12/2026 Corrections Issued KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 3/12/2026 SGSOV Not Ready KEITH EDGHILL
Smoke Detectors 3/12/2026 Approved KEITH EDGHILL
ELECTRICAL-Final 3/19/2026 Approved KEITH EDGHILL
Final 3/19/2026 Corrections Issued KEITH EDGHILL
PLUMBING-Final 3/19/2026 Approved KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 3/19/2026 SGSOV Not Ready KEITH EDGHILL
Final 3/24/2026 Conditional Approval KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Approved KEITH EDGHILL