5415 E ASH ST 90042

Certificate Information: 5415 E ASH ST 90042

Application / Permit
25016-10000-07454
Plan Check / Job No.
B25LA10152
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. REMODEL OF EXISTING 2 STORY SINGLE FAMILY DWELLING. WORK INCLUDES NEW BATHROOMS, KITCHEN REMODEL AND REMOVAL OF ATTACHED GARAGE AND LAUNDRY ROOM.
Permit Issued
Issued on 5/28/2025
Issuing Office
Current Status
Permit Finaled on 5/28/2026

Permit Application Status History

Submitted 3/17/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 ADAM HEGAZI
Corrections Issued 3/20/2025 ADAM HEGAZI
Applicant returned to address corrections 5/14/2025 ADAM HEGAZI
Plan Check Approved 5/27/2025 ADAM HEGAZI
Issued 5/28/2025 APPLICANT
Permit Finaled 5/28/2026 JACOB SEGURA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/9/2025 RUSSELL BONVOULOIR
HPOZ Cleared 5/8/2025 NATHALY DE LA PAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Vega,, Cayetano Gonzalez; Lic. No.: NA43117       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/11/2025 Not Ready for Inspection DAVID WILLIAMS
BUILDING-Rough-Frame 6/26/2025 Corrections Issued JACOB SEGURA
ELECTRICAL-Rough 6/26/2025 Partial Approval JACOB SEGURA
HVAC-Rough 6/26/2025 Partial Approval JACOB SEGURA
PLUMBING-Rough 6/26/2025 Partial Approval JACOB SEGURA
Interior/Exterior Lathing 6/30/2025 Partial Approval JACOB SEGURA
Shower Pan 6/30/2025 Not Ready for Inspection JACOB SEGURA
Excavation/Setback/Form/Re-Bar 7/1/2025 Approved JACOB SEGURA
Insulation 7/1/2025 Approved JACOB SEGURA
HVAC-Rough 7/2/2025 Approved JACOB SEGURA
Interior/Exterior Lathing 7/2/2025 Approved JACOB SEGURA
PLUMBING-Rough 7/2/2025 Approved JACOB SEGURA
Shower Pan 7/2/2025 Approved JACOB SEGURA
BUILDING-Rough-Frame 8/5/2025 Partial Approval JACOB SEGURA
Drywall Nailing 8/5/2025 Approved JACOB SEGURA
Footing/Foundation/Slab 8/5/2025 Corrections Issued JACOB SEGURA
Gas Test 9/3/2025 Partial Approval JACOB SEGURA
Rough-Elec/Plmb/HVAC 9/3/2025 Not Ready for Inspection JACOB SEGURA
BUILDING-Rough-Frame 2/17/2026 Approved JACOB SEGURA
Final 2/17/2026 Corrections Issued JACOB SEGURA
Gas Test 2/17/2026 Approved JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Not Ready JACOB SEGURA
Smoke Detectors 2/17/2026 Not Ready for Inspection JACOB SEGURA
Final 3/6/2026 Partial Approval JACOB SEGURA
Smoke Detectors 3/6/2026 Approved JACOB SEGURA
Final 5/4/2026 Corrections Issued JACOB SEGURA
Footing/Foundation/Slab 5/4/2026 Approved JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 5/4/2026 SGSOV Approved JACOB SEGURA
ELECTRICAL-Final 5/26/2026 Approved JACOB SEGURA
ELECTRICAL-Rough 5/26/2026 Approved JACOB SEGURA
Final 5/26/2026 Conditional Approval JACOB SEGURA
HVAC-Final 5/26/2026 Approved JACOB SEGURA
PLUMBING-Final 5/26/2026 Approved JACOB SEGURA
Final 5/28/2026 Permit Finaled JACOB SEGURA