1822 S GLYNDON AVE 90291

Certificate Information: 1822 S GLYNDON AVE 90291

Application / Permit
25016-10000-06863
Plan Check / Job No.
B25LA09484
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert Existing 366 sq ft detached garage to ADU per state law
Permit Issued
Issued on 4/22/2025
Issuing Office
Current Status
Issued on 4/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/17/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 SUNMIN LEE
Corrections Issued 3/20/2025 SUNMIN LEE
Plan Check Approved 4/15/2025 EDWIN MARTINEZ
Issued 4/22/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/26/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/26/2025 BIAINA HARITUNIAN
Sewer availability Cleared 3/26/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/27/2025 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 4/3/2025 LANNY MERRICK

Contact Information

Contractor Oro Coast Builders Inc; Lic. No.: 1063640-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: NA76761       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/8/2025 Partial Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 5/21/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 5/21/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 6/6/2025 Corrections Issued KENNETH NAGLE
PLUMBING-Rough 6/6/2025 Corrections Issued KENNETH NAGLE
ELECTRICAL-Rough 6/13/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Approved MICHAEL ALLEN
HVAC-Rough 6/13/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 6/13/2025 Approved MICHAEL ALLEN
Special/Order Compliance 6/13/2025 Corrections Issued MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 8/18/2025 Approved JESUS RODRIGUEZ
Insulation 8/18/2025 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 8/18/2025 Approved JESUS RODRIGUEZ
Insulation 8/21/2025 Approved JESUS RODRIGUEZ
Shower Pan 8/28/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 9/2/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 9/9/2025 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/17/2025 Approved JESUS RODRIGUEZ
Drywall Nailing 9/17/2025 Approved JESUS RODRIGUEZ
Green Building Rough 9/17/2025 Approved JESUS RODRIGUEZ
Sewer 9/17/2025 Approved JESUS RODRIGUEZ
Underground Mechanical 9/17/2025 Approved JESUS RODRIGUEZ
Final 3/18/2026 Corrections Issued RUBEN RIVAS
Green Building Final 3/18/2026 Approved RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 3/18/2026 SGSOV Approved RUBEN RIVAS
Smoke Detectors 3/18/2026 Approved RUBEN RIVAS
Final 4/14/2026 Corrections Issued RUBEN RIVAS
Final 4/22/2026 Corrections Issued RUBEN RIVAS
Final 5/21/2026 Corrections Issued RUBEN RIVAS
Final 6/22/2026 Not Ready for Inspection MORRIS JACKSON