13545 W SARAH ST 91423
Certificate Information: 13545 W SARAH ST 91423
- Application / Permit
- 25016-10000-06502
- Plan Check / Job No.
- B25LA08958
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: INTERIOR REMODEL TO KITCHEN, PANTRY, AND DINING ROOM. REMOVE LOW CEILING AT KITCHEN. ENCLOSE EXISTING COVERED PATIO. NEW DOORS AND WINDOWS . PER ENGINEER DESIGN.
- Permit Issued
- Issued on 5/7/2025
- Issuing Office
- Current Status
- Permit Finaled on 9/25/2025
Permit Application Status History
| Submitted | 3/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2025 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 3/13/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 3/20/2025 | MIROOSH KHACHATOORIAN |
| Issued | 5/7/2025 | APPLICANT |
| Permit Finaled | 9/24/2025 | MISAEL ESPARZA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Elise Blaine Construction & Design Inc; Lic. No.: 1076163-B | , |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/5/2025 | Corrections Issued | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 6/9/2025 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 6/9/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/12/2025 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 7/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 7/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 7/23/2025 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 7/23/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/23/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 7/23/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 7/28/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/30/2025 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 7/30/2025 | Conditional Approval | JUAN VALENZUELA |
| Drywall Nailing | 7/30/2025 | Approved | JAVIER RAMOS JR |
| Final | 9/24/2025 | Permit Finaled | MISAEL ESPARZA |
| MERV13>=Final | 9/24/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 9/24/2025 | Approved | MISAEL ESPARZA |