1526 S MALCOLM AVE 90024
Certificate Information: 1526 S MALCOLM AVE 90024
- Application / Permit
- 25016-10000-06429
- Plan Check / Job No.
- B25LA08891
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL TO (E) SFD WITH ATTACHED GARAGE
- Permit Issued
- Issued on 4/9/2025
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2025 | FERNANDO FLORES |
| Corrections Issued | 3/16/2025 | FERNANDO FLORES |
| Building Plans Picked Up | 3/18/2025 | APPLICANT |
| Plan Check Approved | 4/9/2025 | EDWIN MARTINEZ |
| Issued | 4/9/2025 | APPLICANT |
| Permit Finaled | 11/4/2025 | MICHAEL ALLEN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/9/2025 | FERNANDO FLORES |
Contact Information
| Contractor | Ecobuild Pros Inc; Lic. No.: 1111889-B | 14127 MARGATE ST SHERMAN OAKS, CA 91401 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/14/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 4/14/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 4/14/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 4/14/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 4/14/2025 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 4/14/2025 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/16/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 4/16/2025 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 4/16/2025 | Approved | KIRK SANDERS |
| HVAC-Rough | 4/16/2025 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 4/16/2025 | Approved | KIRK SANDERS |
| Drywall Nailing | 4/21/2025 | Approved | EVAN COOPER |
| Insulation | 4/21/2025 | Approved | EVAN COOPER |
| Final | 10/23/2025 | Corrections Issued | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Not Ready | MICHAEL ALLEN |
| Smoke Detectors | 10/23/2025 | Corrections Issued | MICHAEL ALLEN |
| Final | 11/4/2025 | Permit Finaled | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 11/4/2025 | Approved | MICHAEL ALLEN |