206 S UNION PL 1-21 90026

Certificate Information: 206 S UNION PL 1-21 90026

Application / Permit
25016-10000-06223
Plan Check / Job No.
B25LA08684
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT EXISTING STORAGE INTO NEW ACCESSROY DWELLING 20 UNIT MULTI-FAMILY RESIDENCE. PER GCS 65852.2 (e)(1)(C) .
Permit Issued
Issued on 6/12/2025
Issuing Office
Current Status
CofO in Progress on 7/7/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/7/2025 APPLICANT
Assigned to Plan Check Engineer 4/10/2025 PINANK PATEL
Corrections Issued 4/10/2025 PINANK PATEL
Applicant returned to address corrections 5/20/2025 PINANK PATEL
Applicant returned to address corrections 5/22/2025 ROSENDO MEDINA
Plan Check Approved 6/10/2025 ROSENDO MEDINA
Issued 6/12/2025 APPLICANT
CofO in Progress 7/7/2026 REGINA MENDEZ

Permit Application Clearance Information

Address approval Cleared 4/21/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/21/2025 LEE GUILBEAUX
Sewer availability Cleared 5/9/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/9/2025 LEE GUILBEAUX
Historic Resource Verification Cleared 5/15/2025 RAFAEL FONTES
Redevelopment Project Area Cleared 5/15/2025 YASMINE BASHIRI
Fire Marshal Fire Life Safety Cleared 6/5/2025 ANDREW KO

Contact Information

Contractor Owner-Builder       ,
Engineer Vartanian,, Albert; Lic. No.: NA39989       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/16/2025 Partial Approval PAUL BAZERKANIAN
Wood Frame 9/8/2025 Partial Approval PAUL BAZERKANIAN
Insulation 12/12/2025 Partial Approval PAUL BAZERKANIAN
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Partial Approval JEROME BLACKWOOD
METHANE-Rough 12/17/2025 Partial Approval JEROME BLACKWOOD
Drywall Nailing 12/30/2025 Partial Approval PAUL BAZERKANIAN
Interior/Exterior Lathing 12/30/2025 Partial Approval PAUL BAZERKANIAN
Final 3/17/2026 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Final 3/17/2026 Approved JEROME BLACKWOOD
METHANE-Rough 3/17/2026 Approved JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV Not Ready JEROME BLACKWOOD
Smoke Detectors 3/17/2026 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 3/17/2026 Not Ready for Inspection JEROME BLACKWOOD
Final 3/31/2026 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 3/31/2026 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 3/31/2026 Not Ready for Inspection JEROME BLACKWOOD
Final 4/27/2026 Not Ready for Inspection JEROME BLACKWOOD
Smoke Detectors 4/27/2026 Approved JEROME BLACKWOOD
Wood Frame 4/27/2026 Approved JEROME BLACKWOOD
Final 7/2/2026 OK to Issue CofO REGINA MENDEZ