206 S UNION PL 1-21 90026
Certificate Information: 206 S UNION PL 1-21 90026
- Application / Permit
- 25016-10000-06223
- Plan Check / Job No.
- B25LA08684
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT EXISTING STORAGE INTO NEW ACCESSROY DWELLING 20 UNIT MULTI-FAMILY RESIDENCE. PER GCS 65852.2 (e)(1)(C) .
- Permit Issued
- Issued on 6/12/2025
- Issuing Office
- Current Status
- CofO in Progress on 7/7/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2025 | PINANK PATEL |
| Corrections Issued | 4/10/2025 | PINANK PATEL |
| Applicant returned to address corrections | 5/20/2025 | PINANK PATEL |
| Applicant returned to address corrections | 5/22/2025 | ROSENDO MEDINA |
| Plan Check Approved | 6/10/2025 | ROSENDO MEDINA |
| Issued | 6/12/2025 | APPLICANT |
| CofO in Progress | 7/7/2026 | REGINA MENDEZ |
Permit Application Clearance Information
| Address approval | Cleared | 4/21/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/9/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/9/2025 | LEE GUILBEAUX |
| Historic Resource Verification | Cleared | 5/15/2025 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 5/15/2025 | YASMINE BASHIRI |
| Fire Marshal Fire Life Safety | Cleared | 6/5/2025 | ANDREW KO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vartanian,, Albert; Lic. No.: NA39989 | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/16/2025 | Partial Approval | PAUL BAZERKANIAN |
| Wood Frame | 9/8/2025 | Partial Approval | PAUL BAZERKANIAN |
| Insulation | 12/12/2025 | Partial Approval | PAUL BAZERKANIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2025 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Rough | 12/17/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 12/30/2025 | Partial Approval | PAUL BAZERKANIAN |
| Interior/Exterior Lathing | 12/30/2025 | Partial Approval | PAUL BAZERKANIAN |
| Final | 3/17/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| METHANE-Final | 3/17/2026 | Approved | JEROME BLACKWOOD |
| METHANE-Rough | 3/17/2026 | Approved | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 3/17/2026 | SGSOV Not Ready | JEROME BLACKWOOD |
| Smoke Detectors | 3/17/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 3/17/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 3/31/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 3/31/2026 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 3/31/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 3/31/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 4/27/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Smoke Detectors | 4/27/2026 | Approved | JEROME BLACKWOOD |
| Wood Frame | 4/27/2026 | Approved | JEROME BLACKWOOD |
| Final | 7/2/2026 | OK to Issue CofO | REGINA MENDEZ |