2907 S CRENSHAW BLVD 90016

Certificate Information: 2907 S CRENSHAW BLVD 90016

Application / Permit
25016-10000-05832
Plan Check / Job No.
B25LA08066
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Bank
Work Description
REMODEL (E) BANK. INCLUDES NEW EXTERIOR DOOR OPENERS.
Permit Issued
Issued on 10/31/2025
Issuing Office
Metro
Current Status
Issued on 10/31/2025

Permit Application Status History

Submitted 3/3/2025 APPLICANT
Assigned to Plan Check Engineer 3/7/2025 LAWRENCE QUIRANTE
Corrections Issued 3/8/2025 LAWRENCE QUIRANTE
Building Plans Picked Up 3/10/2025 APPLICANT
Applicant returned to address corrections 6/30/2025 CRYSTEL MAALOUF
Applicant returned to address corrections 9/17/2025 JOHN MESIAS
Plan Check Approved 10/28/2025 ADAM HEGAZI
Issued 10/31/2025 APPLICANT

Permit Application Clearance Information

Historic Resource Verification Cleared 10/9/2025 LAMBERT GIESSINGER
Specific Plan Cleared 10/15/2025 ISAIAH ROSS
Redevelopment Project Area Cleared 10/17/2025 YASMINE BASHIRI

Contact Information

Architect Acevedo,, Nicholas James; Lic. No.: C32405 2215 ANNIVERSARY LANE      NEWPORT BEACH, CA 92660
Contractor Fcs Construction Services Inc; Lic. No.: 926254-B 7 WEST FIGUEROA ST STE 300      SANTA BARBARA, CA 93101
Engineer Hoballah,, Tarek Ali; Lic. No.: S4124 2600 E PACIFIC COAST HWY STE 170      LONG BEACH, CA 90804
Engineer Sullivan,, Amie E; Lic. No.: C65030 6211 32ND AVE NW      SEATTLE, WA 98107

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 11/19/2025 No Access for Inspection MARTIN TAVITIAN
Light Gage Steel Frame 11/20/2025 Partial Approval PAUL BAZERKANIAN
Insulation 12/4/2025 Not Ready for Inspection MARTIN TAVITIAN
Drywall Nailing 12/9/2025 Partial Approval RAFAEL CORTES
T-Bar Ceiling 1/14/2026 Approved MARTIN TAVITIAN
Pre-Inspection 1/28/2026 Partial Inspection CHRISTOPHER BLACKWOOD
T-Bar Ceiling 2/5/2026 Partial Approval IAN BLINN
Light Gage Steel Frame 3/3/2026 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Wood Frame 3/3/2026 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Wood Frame 3/4/2026 Partial Approval IAN BLINN
Deputy Drilled-In Anchors 3/6/2026 Partial Approval IAN BLINN
Deputy Steel/Welding 3/6/2026 Partial Approval IAN BLINN
Drywall Nailing 3/6/2026 Partial Approval IAN BLINN
Grading Pre-Inspection 3/13/2026 Not Ready for Inspection MARTIN TAVITIAN
Pre-Inspection 3/13/2026 Approved MARTIN TAVITIAN
Final 3/23/2026 Not Ready for Inspection MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 3/23/2026 SGSOV Not Ready MARTIN TAVITIAN
Smoke Detectors 3/23/2026 Not Ready for Inspection MARTIN TAVITIAN
Drywall Nailing 3/25/2026 Partial Approval IAN BLINN
T-Bar Ceiling 4/3/2026 Partial Approval IAN BLINN
Final 4/9/2026 Not Ready for Inspection IAN BLINN
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Not Ready IAN BLINN
Smoke Detectors 4/9/2026 Not Ready for Inspection IAN BLINN
Final 4/20/2026 Partial Approval IAN BLINN
SGSOV-Seismic Gas S/O Valve 4/20/2026 SGSOV Not Required IAN BLINN
Smoke Detectors 4/20/2026 Approved IAN BLINN