1757 N GARDNER ST 90046

Certificate Information: 1757 N GARDNER ST 90046

Application / Permit
25016-10000-05791
Plan Check / Job No.
B25LA07994
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL (E) 2 STORY SFD SEE COMMENT
Permit Issued
Issued on 7/15/2025
Issuing Office
Current Status
Issued on 7/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/3/2025 APPLICANT
Assigned to Plan Check Engineer 3/7/2025 MINA HABILI
Corrections Issued 3/8/2025 MINA HABILI
Building Plans Picked Up 3/11/2025 APPLICANT
Applicant returned to address corrections 6/24/2025 JOHN MESIAS
Applicant returned to address corrections 6/25/2025 MINA HABILI
Applicant returned to address corrections 7/2/2025 JESSE ARELLANO
Plan Check Approved 7/15/2025 JOHN MESIAS
Issued 7/15/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/16/2025 MICHAEL BROWN
Grading Pre-Inspection Cleared 6/25/2025 MINA HABILI
Roof/Waste drainage to street Cleared 6/26/2025 CELINA MORENO

Contact Information

Contractor Maison Design Build Inc; Lic. No.: 1069284-B 8665 W SUNSET BLVD      LOS ANGELES, CA 90069
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/5/2025 Partial Approval ROY SPAULDING
Deputy Drilled-In Anchors 8/29/2025 Conditional Approval ROY SPAULDING
Deputy Wood Construction 9/3/2025 Conditional Approval ROY SPAULDING
BUILDING-Rough-Frame 9/4/2025 Not Ready for Inspection ROY SPAULDING
Footing/Foundation/Slab 9/4/2025 Corrections Issued ROY SPAULDING
Green Building Rough 9/4/2025 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 9/15/2025 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 9/15/2025 Partial Approval ROY SPAULDING
ELECTRICAL-Rough 10/15/2025 Corrections Issued ROY SPAULDING
HVAC-Rough 10/15/2025 Corrections Issued ROY SPAULDING
PLUMBING-Rough 10/15/2025 Partial Approval ROY SPAULDING
ELECTRICAL-Rough 11/18/2025 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 11/18/2025 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 11/18/2025 Approved CRAIG VAUGHAN
Shower Pan 12/12/2025 Approved ROY SPAULDING
Interior/Exterior Lathing 12/31/2025 Approved ROY SPAULDING
BUILDING-Rough-Frame 1/14/2026 Approved ROY SPAULDING
Green Building Rough 1/14/2026 Approved ROY SPAULDING
HVAC-Rough 1/14/2026 Approved ROY SPAULDING
Insulation 1/21/2026 Not Ready for Inspection ROY SPAULDING
Interior/Exterior Lathing 1/21/2026 Approved ROY SPAULDING
Interior/Exterior Lathing 2/6/2026 Corrections Issued ROY SPAULDING
Interior/Exterior Lathing 2/10/2026 Approved ROY SPAULDING
Drywall Nailing 3/25/2026 Approved ROY SPAULDING