1224 S BEVERWIL DR 90035

Certificate Information: 1224 S BEVERWIL DR 90035

Application / Permit
25016-10000-05688
Plan Check / Job No.
B25LA07830
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
ePlan: Hotel Remodel to public space areas to include lobby, bar, reception desk, restaurant, private dining/meeting rooms and fitness center. New luggage storage room. New trellis at pool deck and restaurant patio. Replace ground level entrance canopy soffit ***"COMPLY WITH DEPARTMENT ORDER effective date 01/11/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 8/29/2025
Issuing Office
Current Status
Issued on 8/29/2025

Permit Application Status History

Submitted 3/4/2025 APPLICANT
Assigned to Zoning Architect 3/6/2025 FRANCIS AHN
Assigned to Plan Check Engineer 3/20/2025 SINA KHOSRAVI
Corrections Issued 4/9/2025 SINA KHOSRAVI
Quality Review Completed 4/17/2025 GARO TELMI
Applicant returned to address corrections 5/21/2025 SINA KHOSRAVI
Plan Check Approved 8/28/2025 SINA KHOSRAVI
Issued 8/29/2025 APPLICANT

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 5/4/2025 FIRE DEPARTMENT
Miscellaneous Cleared 6/3/2025 BRENNEN OBETO
Green Code Cleared 6/24/2025 Ricardo Ramirez Solis
DAS Clearance Cleared 8/14/2025 ELIZABETH TOMS
Zoning Plan Check Cleared 8/15/2025 Ricardo Ramirez Solis
Food establishment approval Cleared 8/28/2025 LACDHS APPROVED

Contact Information

Architect Soisson,, Matthew Richard; Lic. No.: C34384       ,
Contractor First Finish Inc; Lic. No.: 981707-B       ,
Contractor First Finish Llc; Lic. No.: 981707-B       ,
Engineer Lehman,, Max Norwood; Lic. No.: C93758 9800 PYRAMID CT   SUITE 350    ENGLEWOOD, CO 80112

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/25/2025 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 10/6/2025 Partial Approval FARHAD DADBIN
Insulation 10/10/2025 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 10/10/2025 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 10/31/2025 Corrections Issued FARHAD DADBIN
Posting Pre-Inspection 11/10/2025 Not Ready for Inspection FARHAD DADBIN
Pre-Inspection 11/10/2025 Approved FARHAD DADBIN
Light Gage Steel Frame 11/15/2025 Off-Hour Fees Due
Light Gage Steel Frame 11/15/2025 Partial Approval FARHAD DADBIN
Final 11/25/2025 Not Ready for Inspection FARHAD DADBIN
Green Building Final 11/25/2025 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 11/25/2025 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 11/25/2025 Not Ready for Inspection FARHAD DADBIN
Deputy Drilled-In Anchors 1/13/2026 Conditional Approval FARHAD DADBIN
Final 2/3/2026 Corrections Issued FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 2/3/2026 Not Ready for Inspection FARHAD DADBIN
Light Gage Steel Frame 3/13/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 3/18/2026 Partial Approval FARHAD DADBIN
Interior/Exterior Lathing 3/23/2026 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 4/22/2026 Partial Approval FARHAD DADBIN