1224 S BEVERWIL DR 90035
Certificate Information: 1224 S BEVERWIL DR 90035
- Application / Permit
- 25016-10000-05688
- Plan Check / Job No.
- B25LA07830
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- ePlan: Hotel Remodel to public space areas to include lobby, bar, reception desk, restaurant, private dining/meeting rooms and fitness center. New luggage storage room. New trellis at pool deck and restaurant patio. Replace ground level entrance canopy soffit ***"COMPLY WITH DEPARTMENT ORDER effective date 01/11/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 8/29/2025
- Issuing Office
- Current Status
- Issued on 8/29/2025
Permit Application Status History
| Submitted | 3/4/2025 | APPLICANT |
| Assigned to Zoning Architect | 3/6/2025 | FRANCIS AHN |
| Assigned to Plan Check Engineer | 3/20/2025 | SINA KHOSRAVI |
| Corrections Issued | 4/9/2025 | SINA KHOSRAVI |
| Quality Review Completed | 4/17/2025 | GARO TELMI |
| Applicant returned to address corrections | 5/21/2025 | SINA KHOSRAVI |
| Plan Check Approved | 8/28/2025 | SINA KHOSRAVI |
| Issued | 8/29/2025 | APPLICANT |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 5/4/2025 | FIRE DEPARTMENT |
| Miscellaneous | Cleared | 6/3/2025 | BRENNEN OBETO |
| Green Code | Cleared | 6/24/2025 | Ricardo Ramirez Solis |
| DAS Clearance | Cleared | 8/14/2025 | ELIZABETH TOMS |
| Zoning Plan Check | Cleared | 8/15/2025 | Ricardo Ramirez Solis |
| Food establishment approval | Cleared | 8/28/2025 | LACDHS APPROVED |
Contact Information
| Architect | Soisson,, Matthew Richard; Lic. No.: C34384 | , |
| Contractor | First Finish Inc; Lic. No.: 981707-B | , |
| Contractor | First Finish Llc; Lic. No.: 981707-B | , |
| Engineer | Lehman,, Max Norwood; Lic. No.: C93758 | 9800 PYRAMID CT SUITE 350 ENGLEWOOD, CO 80112 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/25/2025 | Partial Approval | FARHAD DADBIN |
| Light Gage Steel Frame | 10/6/2025 | Partial Approval | FARHAD DADBIN |
| Insulation | 10/10/2025 | Partial Approval | FARHAD DADBIN |
| Light Gage Steel Frame | 10/10/2025 | Partial Approval | FARHAD DADBIN |
| Light Gage Steel Frame | 10/31/2025 | Corrections Issued | FARHAD DADBIN |
| Posting Pre-Inspection | 11/10/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Pre-Inspection | 11/10/2025 | Approved | FARHAD DADBIN |
| Light Gage Steel Frame | 11/15/2025 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 11/15/2025 | Partial Approval | FARHAD DADBIN |
| Final | 11/25/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 11/25/2025 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 11/25/2025 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 11/25/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 1/13/2026 | Conditional Approval | FARHAD DADBIN |
| Final | 2/3/2026 | Corrections Issued | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2026 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 2/3/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Light Gage Steel Frame | 3/13/2026 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 3/18/2026 | Partial Approval | FARHAD DADBIN |
| Interior/Exterior Lathing | 3/23/2026 | Partial Approval | FARHAD DADBIN |
| Light Gage Steel Frame | 4/22/2026 | Partial Approval | FARHAD DADBIN |