1409 W 69TH ST 90047
Certificate Information: 1409 W 69TH ST 90047
- Application / Permit
- 25016-10000-05661
- Plan Check / Job No.
- B25LA07778
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE WITH ADDITION TO ADU PER STATE LAW GCS 66323(A)(2), ALL WORK PER WFPP
- Permit Issued
- Issued on 8/18/2025
- Issuing Office
- Current Status
- Issued on 8/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2025 | MINA HABILI |
| Corrections Issued | 3/7/2025 | MINA HABILI |
| Building Plans Picked Up | 3/13/2025 | APPLICANT |
| Applicant returned to address corrections | 4/11/2025 | DANIEL SMILEY |
| Applicant returned to address corrections | 4/18/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 8/18/2025 | NEHEMIAS RAMOS |
| Issued | 8/18/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/29/2025 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 3/29/2025 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2025 | ERIK BEASLEY |
| Sewer availability | Cleared | 4/2/2025 | ERIK BEASLEY |
| Construction near power lines | Cleared | 7/10/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/10/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/8/2025 | Partial Approval | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 9/12/2025 | Corrections Issued | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 9/16/2025 | Corrections Issued | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 9/17/2025 | Partial Approval | BARRY HACHE |
| Deputy Drilled-In Anchors | 9/18/2025 | Conditional Approval | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 9/19/2025 | Approved | LUIS CASTRO |
| Wood Frame | 1/27/2026 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Approved | BARRY HACHE |
| PLUMBING-Rough | 2/3/2026 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 3/13/2026 | Corrections Issued | BARRY HACHE |
| Gas Test | 3/13/2026 | Approved | BARRY HACHE |
| HVAC-Rough | 3/13/2026 | Corrections Issued | BARRY HACHE |
| Interior/Exterior Lathing | 3/13/2026 | Partial Approval | BARRY HACHE |
| PLUMBING-Rough | 3/13/2026 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Rough | 3/27/2026 | Partial Approval | BARRY HACHE |
| ELECTRICAL-Rough | 4/21/2026 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 4/21/2026 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 5/13/2026 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 5/13/2026 | Approved | SABAS ALONSO |
| Green Building Rough | 5/13/2026 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/27/2026 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 5/27/2026 | Approved | WILLIAM SIERRA |
| Insulation | 6/2/2026 | Corrections Issued | ALEX COLIN |