5172 N GLORIA AVE 91436

Certificate Information: 5172 N GLORIA AVE 91436

Application / Permit
25016-10000-05595
Plan Check / Job No.
B25LA07685
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) UNPERMITTED STRUCTURE BUILT PRIOR TO JAN 2020 INTO ADU PER 65852.23 WITH ADDITION PER STATE LAW, ALL WORK PER WFPP "Existing construction does not pose a threat to the public's health and safety was allowed per Government Code Section 55.852.2(d)(2)."
Permit Issued
Issued on 4/10/2025
Issuing Office
Metro
Current Status
Issued on 4/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/28/2025 APPLICANT
Assigned to Plan Check Engineer 3/5/2025 LUKE GONZALES
Corrections Issued 3/7/2025 LUKE GONZALES
Building Plans Picked Up 3/14/2025 APPLICANT
Applicant returned to address corrections 4/9/2025 NEHEMIAS RAMOS
Plan Check Approved 4/10/2025 MINA HABILI
Issued 4/10/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/14/2025 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 3/14/2025 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 3/18/2025 CHRISTINA BRACO
Sewer availability Cleared 3/18/2025 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/30/2025 Corrections Issued ROBERT GOLD
PLUMBING-Rough 5/30/2025 Not Ready for Inspection ROBERT GOLD
Excavation/Setback/Form/Re-Bar 11/19/2025 Not Ready for Inspection JOHN KIDWELL
Gas Test 11/19/2025 Partial Approval JOHN KIDWELL
Sewer 11/19/2025 Approved JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 12/3/2025 Corrections Issued THOMAS FINNILA
ELECTRICAL-Final 2/24/2026 Corrections Issued THOMAS FINNILA
ELECTRICAL-Final 4/13/2026 Corrections Issued THOMAS FINNILA
Green Building Final 4/13/2026 Approved THOMAS FINNILA
HVAC-Final 4/13/2026 Corrections Issued THOMAS FINNILA
PLUMBING-Final 4/13/2026 Corrections Issued THOMAS FINNILA
Verify Rec and Parks Fee Memo 4/13/2026 Approved THOMAS FINNILA
BUILDING-Rough-Frame 4/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 4/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
Final 4/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 4/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Rough 4/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 4/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
MERV13>=Final 4/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
MERV13>=Rough 4/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 4/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 4/18/2026 SGSOV Not Ready ARUTYUN MADATYAN
Service/Power Release 4/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 4/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
Verify Rec and Parks Fee Memo 4/18/2026 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 4/23/2026 Approved THOMAS FINNILA
ELECTRICAL-Final 4/23/2026 Corrections Issued THOMAS FINNILA
Final 4/23/2026 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 4/23/2026 Approved THOMAS FINNILA
Green Building Rough 4/23/2026 Approved THOMAS FINNILA
HVAC-Final 4/23/2026 Corrections Issued THOMAS FINNILA
MERV13>=Rough 4/23/2026 Approved THOMAS FINNILA
PLUMBING-Final 4/23/2026 Corrections Issued THOMAS FINNILA
Service/Power Release 4/27/2026 Approved THOMAS FINNILA