1217 W 77TH ST 90044
Certificate Information: 1217 W 77TH ST 90044
- Application / Permit
- 25016-10000-05230
- Plan Check / Job No.
- B25LA07366
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL EXISTING SFD, RELOCATE KITCHEN AND ADD BATHROOM, REPLACE PLUMBING AND ELECTRICAL PATCH DRYWALL THROUGHOUT AND REPAIR STUCCO
- Permit Issued
- Issued on 3/26/2025
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/30/2025
Permit Application Status History
| Submitted | 2/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2025 | ZAW HAN |
| Corrections Issued | 2/26/2025 | ZAW HAN |
| Applicant returned to address corrections | 3/17/2025 | CARLOS MONTES |
| Plan Check Approved | 3/18/2025 | ZAW HAN |
| Issued | 3/26/2025 | APPLICANT |
| Permit Finaled | 5/29/2025 | JOHN QUINTANILLA |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/28/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/28/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Lajoma Construction Inc; Lic. No.: 864461-B | PO BOX 39459 DOWNEY, CA 90241 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/7/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/7/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Gas Test | 4/7/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 4/7/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/7/2025 | Approved | JOHN QUINTANILLA |
| Rough-Elec/Plmb/HVAC | 4/7/2025 | Partial Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/9/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/9/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 4/9/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 4/11/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 4/16/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 5/27/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 5/27/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 5/27/2025 | Approved | JOHN QUINTANILLA |
| Final | 5/29/2025 | Permit Finaled | JOHN QUINTANILLA |
| Gas Test | 5/29/2025 | Partial Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 5/29/2025 | Approved | JOHN QUINTANILLA |