5059 1/4 E EATON ST 90042
Certificate Information: 5059 1/4 E EATON ST 90042
- Application / Permit
- 25016-10000-05177
- Plan Check / Job No.
- B25LA07268
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. PROPOSED ROOFTOP DECK AND CONVERT THE (E) DET. GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
- Permit Issued
- Issued on 10/14/2025
- Issuing Office
- Current Status
- Issued on 10/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2025 | SARKIS HARABEDIAN |
| Corrections Issued | 2/28/2025 | SARKIS HARABEDIAN |
| Plan Check Approved | 3/16/2025 | SARKIS HARABEDIAN |
| Issued | 10/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2025 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 3/4/2025 | CHRISTINA BRACO |
| Sewer availability | Cleared | 3/4/2025 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2025 | CHRISTINA BRACO |
| Hydrant and Access approval | Cleared | 3/6/2025 | LAVEON RIDER |
| Grading Pre-Inspection | Cleared | 3/16/2025 | SARKIS HARABEDIAN |
Contact Information
| Contractor | Era Construction Services; Lic. No.: 659380-B | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/31/2025 | Conditional Approval | GEM DE OCAMPO |
| Footing/Foundation/Slab | 1/2/2026 | Corrections Issued | RONNIE MEDINA |
| PLUMBING-Rough | 1/2/2026 | Corrections Issued | RONNIE MEDINA |
| Excavation/Setback/Form/Re-Bar | 1/8/2026 | Corrections Issued | DAVID WILLIAMS |
| Footing/Foundation/Slab | 1/8/2026 | Corrections Issued | DAVID WILLIAMS |
| PLUMBING-Rough | 1/8/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Underground Mechanical | 1/8/2026 | Partial Approval | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 1/9/2026 | Conditional Approval | RONNIE MEDINA |
| Footing/Foundation/Slab | 1/20/2026 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2026 | Partial Approval | RONNIE MEDINA |
| Footing/Foundation/Slab | 2/18/2026 | Approved | RONNIE MEDINA |
| Rough-Elec/Plmb/HVAC | 2/26/2026 | Approved | DAVID WILLIAMS |
| Underground Mechanical | 3/2/2026 | Partial Approval | RONNIE MEDINA |
| BUILDING-Rough-Frame | 3/19/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Green Building Rough | 3/19/2026 | Not Ready for Inspection | RONNIE MEDINA |
| BUILDING-Rough-Frame | 3/25/2026 | Approved | RONNIE MEDINA |
| Green Building Rough | 3/25/2026 | Approved | RONNIE MEDINA |
| Insulation | 4/6/2026 | Approved | RONNIE MEDINA |
| PLUMBING-Rough | 4/6/2026 | Partial Approval | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2026 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 4/16/2026 | Partial Approval | GEM DE OCAMPO |
| Shower Pan | 4/16/2026 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 4/22/2026 | Approved | RONNIE MEDINA |