236 S TAVISTOCK AVE 90049

Certificate Information: 236 S TAVISTOCK AVE 90049

Application / Permit
25016-10000-04776
Plan Check / Job No.
B25LA06595
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: CONVERT (E) DETACHED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
Permit Issued
Issued on 9/19/2025
Issuing Office
Current Status
CofO in Progress on 2/3/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/24/2025 APPLICANT
Assigned to Plan Check Engineer 2/27/2025 NAREG ATARIAN
Corrections Issued 2/27/2025 NAREG ATARIAN
Applicant returned to address corrections 8/6/2025 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 8/12/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 8/14/2025 ISIS ARGUETA
Issued 9/19/2025 APPLICANT
CofO in Progress 2/3/2026 EVAN COOPER

Permit Application Clearance Information

Address approval Cleared 4/18/2025 XOCHITL ARQUIETA
Sewer availability Cleared 4/18/2025 XOCHITL ARQUIETA
Grading Pre-Inspection Cleared 4/18/2025 LANNY MERRICK
Eng Process Fee Ord 176,300 Cleared 4/21/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 8/13/2025 WALLIE JONG

Contact Information

Contractor H A R Construction Co; Lic. No.: 894345-B       ,
Contractor Harco Builders Inc; Lic. No.: 894345-B       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/2/2025 Not Ready for Inspection DANIEL VERA
Sewer 10/2/2025 Not Ready for Inspection DANIEL VERA
Underground Mechanical 10/2/2025 Corrections Issued DANIEL VERA
Sewer 10/3/2025 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 10/8/2025 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/8/2025 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 10/10/2025 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 10/15/2025 Approved DANIEL VERA
Interior/Exterior Lathing 11/4/2025 Not Ready for Inspection CARLOS MATAMOROS
Wood Frame 11/4/2025 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 11/7/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 11/10/2025 Approved DANIEL VERA
ELECTRICAL-Rough 11/10/2025 Approved DANIEL VERA
Green Building Rough 11/10/2025 Approved DANIEL VERA
HVAC-Rough 11/10/2025 Approved DANIEL VERA
PLUMBING-Rough 11/10/2025 Approved DANIEL VERA
Insulation 11/13/2025 Approved SEAN HAUPT
Shower Pan 11/13/2025 Approved SEAN HAUPT
Shower Pan 11/14/2025 Not Ready for Inspection DANIEL VERA
Drywall Nailing 11/21/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 12/4/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Final 1/14/2026 Corrections Issued EVAN COOPER
Final 1/14/2026 Corrections Issued EVAN COOPER
Green Building Final 1/14/2026 Approved EVAN COOPER
HVAC-Final 1/14/2026 Approved EVAN COOPER
PLUMBING-Final 1/14/2026 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/14/2026 SGSOV Approved EVAN COOPER
Smoke Detectors 1/14/2026 Approved EVAN COOPER
ELECTRICAL-Final 1/21/2026 Approved EVAN COOPER
Final 1/21/2026 Corrections Issued EVAN COOPER
HVAC-Final 1/21/2026 Approved EVAN COOPER
PLUMBING-Final 1/21/2026 Approved EVAN COOPER
Final 2/3/2026 OK to Issue CofO EVAN COOPER