5914 W ABERNATHY DR 90045
Certificate Information: 5914 W ABERNATHY DR 90045
- Application / Permit
- 25016-10000-04737
- Plan Check / Job No.
- B25LA06524
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 4/16/2025
- Issuing Office
- Current Status
- CofO Issued on 7/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2025 | ROSENDO MEDINA |
| Plan Check Approved | 4/14/2025 | ROSENDO MEDINA |
| Issued | 4/16/2025 | APPLICANT |
| CofO in Progress | 7/2/2025 | RUBEN RIVAS |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
| CofO Issued | 7/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2025 | DARIN LAM |
| Sewer availability | Cleared | 2/25/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2025 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 2/27/2025 | VASIL MIHALEV |
| Specific Plan | Cleared | 3/4/2025 | RICHARD WOO |
| Construction near power lines | Cleared | 4/7/2025 | RIDWAN HARDY |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Guideline Builders Inc; Lic. No.: 1021305-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/2/2025 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 5/2/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 5/2/2025 | Partial Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 5/14/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | JESUS PINEDA |
| HVAC-Rough | 5/14/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/14/2025 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 5/14/2025 | Approved | JESUS PINEDA |
| Sewer | 5/14/2025 | Approved | JESUS PINEDA |
| Underground Mechanical | 5/14/2025 | Partial Approval | JESUS PINEDA |
| Insulation | 5/15/2025 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/16/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Approved | JESUS PINEDA |
| Green Building Rough | 5/16/2025 | Approved | JESUS PINEDA |
| Insulation | 5/16/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 5/19/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/22/2025 | Approved | JESUS PINEDA |
| Shower Pan | 5/22/2025 | Approved | JESUS PINEDA |
| Final | 6/23/2025 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 6/23/2025 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2025 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 6/23/2025 | Approved | ARAM AVEDISIAN |
| Final | 6/30/2025 | OK to Issue CofO | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 6/30/2025 | SGSOV Approved | RUBEN RIVAS |