2756 W LOCKSLEY PL 90039

Certificate Information: 2756 W LOCKSLEY PL 90039

Application / Permit
25016-10000-04540
Plan Check / Job No.
B25LA06276
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert (E) Detached garage and conversion of an existing 21' x 13-6" unpermitted structure built prior to Jan 1 2020 to an Accessory Dwelling Unit (348 sq ft) COMPLY WITH DEPARTMENT ORDER effective date 03/29/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 3/18/2025
Issuing Office
Current Status
CofO in Progress on 4/22/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/19/2025 APPLICANT
Assigned to Plan Check Engineer 2/24/2025 FERNANDO FLORES
Corrections Issued 2/25/2025 FERNANDO FLORES
Plan Check Approved 3/17/2025 FERNANDO FLORES
Issued 3/18/2025 APPLICANT
CofO in Progress 4/22/2026 JOEL ORDAZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/4/2025 PAMELA TENEZA
Grading Pre-Inspection Cleared 3/4/2025 MICHAEL TEMPLE
Construction near power lines Cleared 3/6/2025 ENRIQUE ACOSTA
Address approval Cleared 3/7/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 3/7/2025 TAL SHEMEN
Sewer availability Cleared 3/12/2025 TAL SHEMEN

Contact Information

Architect Vilppu,, Lydia Nadine; Lic. No.: NA31349       ,
Contractor Owner-Builder       ,

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JONATHAN FRANCHINI, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/6/2025 Corrections Issued JONATHAN FRANCHINI
Excavation/Setback/Form/Re-Bar 8/8/2025 Approved JOEL ORDAZ
Footing/Foundation/Slab 8/8/2025 Corrections Issued JOEL ORDAZ
ELECTRICAL-Rough 9/25/2025 Not Ready for Inspection JOEL ORDAZ
HVAC-Rough 9/25/2025 Not Ready for Inspection JOEL ORDAZ
PLUMBING-Rough 9/25/2025 Not Ready for Inspection JOEL ORDAZ
Underground Mechanical 9/25/2025 Not Ready for Inspection JOEL ORDAZ
Wood Frame 9/25/2025 Not Ready for Inspection JOEL ORDAZ
ELECTRICAL-Rough 9/29/2025 Not Ready for Inspection JOEL ORDAZ
PLUMBING-Rough 9/29/2025 Approved JOEL ORDAZ
BUILDING-Rough-Frame 10/2/2025 Approved JOEL ORDAZ
ELECTRICAL-Rough 10/2/2025 Corrections Issued JOEL ORDAZ
Green Building Rough 10/2/2025 Approved JOEL ORDAZ
MERV13>=Rough 10/2/2025 Approved JOEL ORDAZ
Insulation 10/17/2025 Approved JOEL ORDAZ
Interior/Exterior Lathing 10/17/2025 Approved JOEL ORDAZ
Drywall Nailing 10/22/2025 Approved JOEL ORDAZ
Final 12/5/2025 Not Ready for Inspection JONATHAN FRANCHINI
Green Building Final 12/5/2025 Corrections Issued JONATHAN FRANCHINI
MERV13>=Final 12/5/2025 Approved JONATHAN FRANCHINI
SGSOV-Seismic Gas S/O Valve 12/5/2025 SGSOV Approved JONATHAN FRANCHINI
Smoke Detectors 12/5/2025 Approved JONATHAN FRANCHINI
ELECTRICAL-Final 1/15/2026 Approved JONATHAN FRANCHINI
Final 1/15/2026 Partial Approval JONATHAN FRANCHINI
Gas Test 1/15/2026 Approved JONATHAN FRANCHINI
Green Building Final 1/15/2026 Approved JONATHAN FRANCHINI
HVAC-Final 1/15/2026 Approved JONATHAN FRANCHINI
PLUMBING-Final 1/15/2026 Approved JONATHAN FRANCHINI
Final 4/22/2026 OK to Issue CofO JOEL ORDAZ