3327 W OBAMA BLVD 90018

Certificate Information: 3327 W OBAMA BLVD 90018

Application / Permit
25016-10000-04532
Plan Check / Job No.
B25LA06270
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO EXISTING SINGLE FAMILY DWELLING TO REMOVE AND REPLACE ROOF FRAMING OVER ENTIRE STRUCTURE, REMOVE AND REPLACE ALL WINDOWS AND DOORS. ALL WORK PER ENGINEER DESIGN.
Permit Issued
Issued on 3/28/2025
Issuing Office
Current Status
Permit Finaled on 3/17/2026

Permit Application Status History

Submitted 2/18/2025 APPLICANT
Assigned to Plan Check Engineer 2/21/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 2/23/2025 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 3/19/2025 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 3/22/2025 MADISON O'DELL
Issued 3/28/2025 APPLICANT
Permit Finaled 3/17/2026 WILLIAM MICHALAK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/4/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 3/4/2025 DAVID LOPEZ
Sewer availability Cleared 3/4/2025 DAVID LOPEZ

Contact Information

Contractor L & E Assets Inc; Lic. No.: 946841-B       ,
Contractor Turquoise Construction; Lic. No.: 946841-B       ,
Engineer Hansen,, Hans Christian; Lic. No.: C80546 12831 MALENA DR      SANTA ANA, CA 92705

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Partial Approval WILLIAM MICHALAK
Interior/Exterior Lathing 9/12/2025 Corrections Issued WILLIAM MICHALAK
Interior/Exterior Lathing 9/29/2025 Approved LUIS CORRAL
ELECTRICAL-Rough 10/15/2025 Corrections Issued WILLIAM MICHALAK
PLUMBING-Rough 10/15/2025 Corrections Issued WILLIAM MICHALAK
BUILDING-Rough-Frame 10/23/2025 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 10/23/2025 Corrections Issued WILLIAM MICHALAK
Insulation 10/27/2025 Approved LUIS CORRAL
Drywall Nailing 10/31/2025 Approved LUIS CORRAL
BUILDING-Rough-Frame 3/10/2026 Approved WILLIAM MICHALAK
Final 3/10/2026 Corrections Issued WILLIAM MICHALAK
Green Building Final 3/10/2026 Approved WILLIAM MICHALAK
Green Building Rough 3/10/2026 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 3/10/2026 Approved WILLIAM MICHALAK
Final 3/17/2026 Permit Finaled WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV Approved WILLIAM MICHALAK