6722-6724 N HESPERIA AVE 91335
Certificate Information: 6722-6724 N HESPERIA AVE 91335
- Application / Permit
- 25016-10000-04482
- Plan Check / Job No.
- B25LA06229
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. conversion of (e) attach garage to JADU
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Current Status
- CofO Issued on 9/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2025 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/22/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/6/2025 | MOHAMMAD ESMAILI |
| Issued | 3/20/2025 | APPLICANT |
| CofO in Progress | 8/25/2025 | JUAN ALVARADO |
| Permit Finaled | 9/6/2025 | MICHAEL PELHAM |
| CofO Issued | 9/6/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/6/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2025 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2025 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 2/26/2025 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/23/2025 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 4/23/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/23/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 4/23/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 5/9/2025 | Approved | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 5/9/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 5/9/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 5/13/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 5/13/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 5/13/2025 | Approved | JUAN ALVARADO |
| Gas Test | 5/15/2025 | Approved | JUAN ALVARADO |
| Insulation | 5/15/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 5/15/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 5/23/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 7/21/2025 | Corrections Issued | JUAN ALVARADO |
| Final | 7/21/2025 | Corrections Issued | JUAN ALVARADO |
| HVAC-Final | 7/21/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 7/21/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 7/21/2025 | SGSOV Not Ready | JUAN ALVARADO |
| Smoke Detectors | 7/21/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 8/4/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 8/14/2025 | Approved | JUAN ALVARADO |
| Final | 8/14/2025 | Partial Approval | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Approved | JUAN ALVARADO |
| Final | 8/22/2025 | OK to Issue CofO | JUAN ALVARADO |
| Service/Power Release | 8/22/2025 | Approved | JUAN ALVARADO |