536 S DALEHURST AVE 90024
Certificate Information: 536 S DALEHURST AVE 90024
- Application / Permit
- 25016-10000-04186
- Plan Check / Job No.
- B25LA05888
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. First floor remodel of existing two story single family dwelling. Work includes including removing loadbearing wall at first floor between bathroom and bedroom and relocating bedroom and bathroom first floor.
- Permit Issued
- Issued on 3/13/2025
- Issuing Office
- Current Status
- Permit Finaled on 11/14/2025
Permit Application Status History
| Submitted | 2/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2025 | NAREG ATARIAN |
| Corrections Issued | 2/15/2025 | NAREG ATARIAN |
| Plan Check Approved | 3/7/2025 | NAREG ATARIAN |
| Issued | 3/13/2025 | APPLICANT |
| Permit Finaled | 11/14/2025 | DANIEL VERA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/27/2025 | VASIL MIHALEV |
Contact Information
| Contractor | Double 88 Construction Inc; Lic. No.: 1052973-B | 6677 SANTA MONICA BLVD APT 4508 LOS ANGELES, CA 90038 |
| Engineer | Standley,, Craig Erick; Lic. No.: NA87675 | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/11/2025 | Conditional Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 8/15/2025 | Conditional Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/15/2025 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 8/15/2025 | Approved | CARLOS MATAMOROS |
| Insulation | 8/15/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/15/2025 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 8/20/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 8/20/2025 | Approved | DANIEL VERA |
| Shower Pan | 8/20/2025 | Not Ready for Inspection | DANIEL VERA |
| Shower Pan | 8/25/2025 | Approved | DANIEL VERA |
| Final | 10/9/2025 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 10/9/2025 | Corrections Issued | STEPHANIE SWANSON |
| Final | 11/14/2025 | Permit Finaled | DANIEL VERA |
| Smoke Detectors | 11/14/2025 | Approved | DANIEL VERA |