1108 S GAYLEY AVE 90024
Certificate Information: 1108 S GAYLEY AVE 90024
- Application / Permit
- 25016-10000-04033
- Plan Check / Job No.
- B24LA38650
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- EPLAN: TENANT IMPROVEMENT TO (E) RESTAURANT
- Permit Issued
- Issued on 6/11/2025
- Issuing Office
- Current Status
- Permit Finaled on 1/20/2026
Permit Application Status History
| Submitted | 2/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2025 | GURUNATH NESARAJAH |
| Corrections Issued | 2/20/2025 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/9/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 4/17/2025 | GURUNATH NESARAJAH |
| Issued | 6/11/2025 | APPLICANT |
| Permit Finaled | 1/16/2026 | PAUL DAVIDSON |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/3/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 3/3/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 3/3/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 3/3/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 3/3/2025 | JAZMIN ROQUE |
| "D" conditions | Cleared | 3/5/2025 | JACKSON OLSON |
| Miscellaneous | Cleared | 3/5/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 3/5/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 3/5/2025 | JAZMIN ROQUE |
| Specific Plan | Cleared | 3/5/2025 | JACKSON OLSON |
| Specific Plan | Cleared | 3/5/2025 | JACKSON OLSON |
| Specific Plan | Cleared | 3/5/2025 | JACKSON OLSON |
| ZA Case | Cleared | 3/11/2025 | RICARDO MARTINEZ |
Contact Information
| Architect | Chiu,, Patrick Sin; Lic. No.: C12852 | 320 W CLARY AVENUE SAN GABRIEL, CA 91776 |
| Architect | Chiu,, Patrick Sin; Lic. No.: NA12852 | , |
| Contractor | Optima Group Inc; Lic. No.: 1049892-B | , |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/24/2025 | Approved | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 7/28/2025 | Conditional Approval | RICARDO ROBLES |
| Excavation/Setback/Form/Re-Bar | 7/29/2025 | Approved | FARHAD DADBIN |
| Light Gage Steel Frame | 7/29/2025 | Approved | FARHAD DADBIN |
| Drywall Nailing | 8/5/2025 | Approved | VASIL MIHALEV |
| T-Bar Ceiling | 12/3/2025 | Approved | PAUL DAVIDSON |
| Final | 1/16/2026 | Permit Finaled | PAUL DAVIDSON |
| Pre-Inspection | 1/16/2026 | Partial Inspection | ROGELIO REYNA |
| SGSOV-Seismic Gas S/O Valve | 1/16/2026 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 1/16/2026 | Approved | PAUL DAVIDSON |