438 N BERNAL AVE 90063
Certificate Information: 438 N BERNAL AVE 90063
- Application / Permit
- 25016-10000-03920
- Plan Check / Job No.
- B25LA05467
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. CONVERT EXISTING DETACHED GARAGE AND STORAGE INTO (N) ACCESSORY DWELLING UNIT PER GC 66323(a)(1). NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT
- Permit Issued
- Issued on 3/10/2025
- Issuing Office
- Current Status
- CofO Issued on 1/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2025 | OMAR GARNICA |
| Corrections Issued | 2/17/2025 | OMAR GARNICA |
| Plan Check Approved | 3/6/2025 | OMAR GARNICA |
| Issued | 3/10/2025 | APPLICANT |
| CofO in Progress | 1/8/2026 | CHARLES BOGHOSKHAN |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
| CofO Issued | 1/9/2026 | DEROLD HAUFF |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2025 | ERIK BEASLEY |
| Sewer availability | Cleared | 2/23/2025 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2025 | ERIK BEASLEY |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/17/2025 | Partial Approval | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 3/24/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/14/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/14/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 8/14/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 8/21/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 8/25/2025 | Partial Approval | ANTHONY RAMOS |
| Drywall Nailing | 9/12/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 9/12/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 12/11/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 12/11/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 12/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 12/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 12/11/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/11/2025 | SGSOV No Gas | ALIZAH MAYAGOITIA |
| Service/Power Release | 12/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 12/11/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 12/22/2025 | No Access for Inspection | FREDDIE RIVERA |
| Final | 12/22/2025 | No Access for Inspection | FREDDIE RIVERA |
| Green Building Final | 12/22/2025 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 12/22/2025 | No Access for Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 12/22/2025 | No Access for Inspection | FREDDIE RIVERA |
| Final | 12/29/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Green Building Final | 12/29/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 12/29/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 12/29/2025 | Approved | ALIZAH MAYAGOITIA |