438 N BERNAL AVE 90063

Certificate Information: 438 N BERNAL AVE 90063

Application / Permit
25016-10000-03920
Plan Check / Job No.
B25LA05467
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. CONVERT EXISTING DETACHED GARAGE AND STORAGE INTO (N) ACCESSORY DWELLING UNIT PER GC 66323(a)(1). NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT
Permit Issued
Issued on 3/10/2025
Issuing Office
Current Status
CofO Issued on 1/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2025 APPLICANT
Assigned to Plan Check Engineer 2/14/2025 OMAR GARNICA
Corrections Issued 2/17/2025 OMAR GARNICA
Plan Check Approved 3/6/2025 OMAR GARNICA
Issued 3/10/2025 APPLICANT
CofO in Progress 1/8/2026 CHARLES BOGHOSKHAN
Permit Finaled 1/9/2026 DEROLD HAUFF
CofO Issued 1/9/2026 DEROLD HAUFF
Permit Finaled 1/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/23/2025 ERIK BEASLEY
Sewer availability Cleared 2/23/2025 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 2/24/2025 ERIK BEASLEY

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/17/2025 Partial Approval NICHOLAS LOPEZ
Footing/Foundation/Slab 3/24/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/14/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 8/14/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 8/14/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 8/14/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 8/14/2025 Approved ALIZAH MAYAGOITIA
Insulation 8/21/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 8/25/2025 Partial Approval ANTHONY RAMOS
Drywall Nailing 9/12/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 9/12/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 12/11/2025 Approved ALIZAH MAYAGOITIA
Final 12/11/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 12/11/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 12/11/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 12/11/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV No Gas ALIZAH MAYAGOITIA
Service/Power Release 12/11/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 12/11/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 12/22/2025 No Access for Inspection FREDDIE RIVERA
Final 12/22/2025 No Access for Inspection FREDDIE RIVERA
Green Building Final 12/22/2025 Corrections Issued FREDDIE RIVERA
HVAC-Final 12/22/2025 No Access for Inspection FREDDIE RIVERA
PLUMBING-Final 12/22/2025 No Access for Inspection FREDDIE RIVERA
Final 12/29/2025 OK to Issue CofO ALIZAH MAYAGOITIA
Green Building Final 12/29/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 12/29/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 12/29/2025 Approved ALIZAH MAYAGOITIA