2624 S BEDFORD ST 90034
Certificate Information: 2624 S BEDFORD ST 90034
- Application / Permit
- 25016-10000-03835
- Plan Check / Job No.
- B25LA05322
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DET GARAGE TO (N) ACCESSORY DWELLING UNIT PER GC 66323(a)(1) "COMPLY WITH DEPARTMENT ORDER effective date 02/19/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 4/6/2025
- Issuing Office
- Current Status
- Issued on 4/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/19/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 2/20/2025 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 3/28/2025 | LUISANGEL VALENZUELA |
| Issued | 4/6/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/20/2025 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 2/20/2025 | CHRISTINA BRACO |
| Sewer availability | Cleared | 2/20/2025 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2025 | CELINA MORENO |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | , |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/4/2025 | Partial Approval | MICHAEL ALLEN |
| Underground Mechanical | 9/4/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 9/9/2025 | Approved | WILLIAM MICHALAK |
| Rough-Elec/Plmb/HVAC | 9/29/2025 | Corrections Issued | WILLIAM MICHALAK |
| Sewer | 9/29/2025 | Not Ready for Inspection | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 10/1/2025 | Partial Approval | WILLIAM MICHALAK |
| Green Building Rough | 10/1/2025 | Partial Approval | WILLIAM MICHALAK |
| MERV13>=Rough | 10/1/2025 | Approved | WILLIAM MICHALAK |
| Rough-Elec/Plmb/HVAC | 10/1/2025 | Partial Approval | WILLIAM MICHALAK |
| Wood Frame | 10/1/2025 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 10/3/2025 | Partial Approval | WILLIAM MICHALAK |
| Shower Pan | 10/3/2025 | Approved | WILLIAM MICHALAK |
| Sewer | 10/22/2025 | Corrections Issued | WILLIAM MICHALAK |
| Sewer | 10/27/2025 | Corrections Issued | WILLIAM MICHALAK |
| Sewer | 10/28/2025 | Partial Approval | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 11/5/2025 | Partial Approval | WILLIAM MICHALAK |
| Green Building Rough | 11/5/2025 | Partial Approval | WILLIAM MICHALAK |
| Insulation | 11/5/2025 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 11/5/2025 | Approved | WILLIAM MICHALAK |
| Rough-Elec/Plmb/HVAC | 11/5/2025 | Approved | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Corrections Issued | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2025 | Corrections Issued | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2025 | Approved | WILLIAM MICHALAK |
| Drywall Nailing | 11/26/2025 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Rough | 11/26/2025 | Approved | WILLIAM MICHALAK |
| Drywall Nailing | 12/2/2025 | Approved | LUIS CORRAL |
| BUILDING-Rough-Frame | 12/23/2025 | Approved | WILLIAM MICHALAK |
| Final | 12/23/2025 | Corrections Issued | WILLIAM MICHALAK |
| Green Building Final | 12/23/2025 | Partial Approval | WILLIAM MICHALAK |
| MERV13>=Final | 12/23/2025 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 12/23/2025 | Approved | WILLIAM MICHALAK |
| Final | 12/31/2025 | Not Ready for Inspection | LUIS CORRAL |
| Green Building Final | 12/31/2025 | Approved | LUIS CORRAL |
| SGSOV-Seismic Gas S/O Valve | 12/31/2025 | SGSOV Approved | LUIS CORRAL |