2918 S CLUNE AVE 90291

Certificate Information: 2918 S CLUNE AVE 90291

Application / Permit
25016-10000-03770
Plan Check / Job No.
B25LA05246
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: INTERIOR REMODEL TO (E) SFD, ALL WORK PER ENG.
Permit Issued
Issued on 4/8/2025
Issuing Office
Current Status
Permit Finaled on 5/7/2026

Permit Application Status History

Submitted 2/11/2025 APPLICANT
Assigned to Plan Check Engineer 2/14/2025 LUISANGEL VALENZUELA
Corrections Issued 2/15/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/25/2025 LUISANGEL VALENZUELA
Plan Check Approved 3/28/2025 LUISANGEL VALENZUELA
Issued 4/8/2025 APPLICANT
Permit Finaled 5/6/2026 RUBEN RIVAS

Permit Application Clearance Information

Coastal Zone Cleared 2/25/2025 BRENNEN OBETO

Contact Information

Contractor Royal Family Construction Inc; Lic. No.: 1082702-B       ,
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/10/2025 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 4/16/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 7/15/2025 No Access for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/16/2025 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/21/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 7/22/2025 Corrections Issued MICHAEL ALLEN
PLUMBING-Rough 7/22/2025 Corrections Issued MICHAEL ALLEN
ELECTRICAL-Rough 7/23/2025 No Access for Inspection TEMISTOCLES CAAL
ELECTRICAL-Rough 7/24/2025 Corrections Issued TEMISTOCLES CAAL
HVAC-Rough 7/24/2025 Corrections Issued TEMISTOCLES CAAL
Special/Order Compliance 7/24/2025 Partial Inspection HERBERT GIRON
BUILDING-Rough-Frame 8/1/2025 Approved JESUS RODRIGUEZ
Green Building Rough 8/1/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 8/1/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/1/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 8/1/2025 Approved JESUS RODRIGUEZ
Insulation 8/11/2025 Corrections Issued JESUS RODRIGUEZ
Insulation 8/13/2025 Not Ready for Inspection JESUS RODRIGUEZ
Special/Order Compliance 8/13/2025 Partial Inspection JAYLIN GRAVITTE
Insulation 8/20/2025 Approved JESUS RODRIGUEZ
Drywall Nailing 8/22/2025 Approved MICHAEL ALLEN
Final 9/11/2025 Not Ready for Inspection JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/11/2025 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 9/11/2025 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Corrections Issued JESUS RODRIGUEZ
Underground Mechanical 11/3/2025 Approved JESUS RODRIGUEZ
Final 12/4/2025 Corrections Issued RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Not Required RUBEN RIVAS
Smoke Detectors 12/4/2025 Approved RUBEN RIVAS
Final 12/10/2025 Corrections Issued RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 12/10/2025 SGSOV Approved RUBEN RIVAS
Final 12/15/2025 Corrections Issued RUBEN RIVAS
Final 12/22/2025 Corrections Issued RUBEN RIVAS
Final 5/6/2026 Permit Finaled RUBEN RIVAS