6305 E YORK BLVD 90042
Certificate Information: 6305 E YORK BLVD 90042
- Application / Permit
- 25016-10000-03757
- Plan Check / Job No.
- B25LA05214
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- Remodel of an existing building into new retail store. Scope of work involves new interior build-out including partitions, doors, ceiling finishes, millwork, and under separate permits: all associated mechanical, electrical and plumbing work. Exterior work involves modifications to existing building shell to accommodate new storefront entry doors and finishes.
- Permit Issued
- Issued on 5/6/2025
- Issuing Office
- Current Status
- Permit Finaled on 9/30/2025
Permit Application Status History
| Submitted | 2/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | JOE VO |
| Assigned to Zoning Architect | 2/13/2025 | LY CHEA |
| Corrections Issued | 2/16/2025 | JOE VO |
| Quality Review Completed | 2/18/2025 | GARO TELMI |
| Plan Check Approved | 5/5/2025 | JOE VO |
| Issued | 5/6/2025 | APPLICANT |
| Permit Finaled | 9/30/2025 | JEROME BLACKWOOD |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/26/2025 | DANIEL CORONADO |
| Green Code | Cleared | 4/3/2025 | AARON COSTA |
| DAS Clearance | Cleared | 4/22/2025 | ELIZABETH TOMS |
| Zoning Plan Check | Cleared | 4/25/2025 | Luke Gonzales |
Contact Information
| Architect | Tricarico,, Nicholas J; Lic. No.: NA15102 | , |
| Contractor | Kershaw Construction Inc; Lic. No.: 735516-B | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 5/12/2025 | Partial Inspection | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 6/4/2025 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 6/4/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Light Gage Steel Frame | 6/5/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 6/9/2025 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 6/16/2025 | Partial Inspection | JEROME BLACKWOOD |
| Wood Frame | 6/25/2025 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 6/26/2025 | Partial Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 7/2/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 7/8/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 7/14/2025 | Approved | RONALD JIMENEZ |
| T-Bar Ceiling | 7/25/2025 | Approved | JEROME BLACKWOOD |
| Final | 9/3/2025 | Conditional Approval | RONALD JIMENEZ |
| Green Building Final | 9/3/2025 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 9/3/2025 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 9/3/2025 | Approved | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 9/17/2025 | Partial Approval | RAFAEL CORTES |
| Final | 9/30/2025 | Permit Finaled | JEROME BLACKWOOD |