4861 W CLINTON ST 90004

Certificate Information: 4861 W CLINTON ST 90004

Application / Permit
25016-10000-03661
Plan Check / Job No.
X25LA05073
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Replacement of damaged framing members (less than 10% of replacement cost of building) for houses and duplexes (not including decks). Water damage repair less than 10% of replacement cost of residential buildings. Replace drywall (no new walls added) for single family dwellings and duplexes only. Install radiant barrier and/or insulation in attic for residential buildings. (12) Window and (3) door change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council (NFRC), is required for doors and windows replaced in all residential buildings, three stories or less, per Section 150.2(b) 1B of Title 24. Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over EXISTING solid sheathing __12__Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone (VHFHSZ). For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council (CRRC). Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0(b) 2B.
Permit Issued
Issued on 2/10/2025
Issuing Office
Metro
Current Status
Permit Finaled on 3/25/2026

Permit Application Status History

Issued 2/10/2025 APPLICANT
Permit Finaled 3/24/2026 JEFFREY MEAD

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Echo Projects Inc; Lic. No.: 1075789-B 1506 WALLACE AVENUE      LOS ANGELES, CA 90026

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Partial Approval JEFFREY MEAD
Green Building Rough 5/29/2025 Not Ready for Inspection JEFFREY MEAD
Wood Frame 5/29/2025 Not Ready for Inspection JEFFREY MEAD
Wood Frame 7/25/2025 Approved JEFFREY MEAD
Final 3/24/2026 Permit Finaled JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Approved JEFFREY MEAD
Smoke Detectors 3/24/2026 Approved JEFFREY MEAD