1189 E MONTECITO DR 90031
Certificate Information: 1189 E MONTECITO DR 90031
- Application / Permit
- 25016-10000-03385
- Plan Check / Job No.
- B25LA04694
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert detached garage into new ADU per state law.
- Permit Issued
- Issued on 4/18/2025
- Issuing Office
- Current Status
- CofO Issued on 4/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2025 | JOHN MESIAS |
| Corrections Issued | 3/11/2025 | JOHN MESIAS |
| Applicant returned to address corrections | 4/9/2025 | JOHN MESIAS |
| Applicant returned to address corrections | 4/15/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 4/17/2025 | NEHEMIAS RAMOS |
| Issued | 4/18/2025 | APPLICANT |
| CofO in Progress | 4/9/2026 | LILIANA PORTILLO |
| Permit Finaled | 4/10/2026 | DEROLD HAUFF |
| Permit Finaled | 4/10/2026 | DEROLD HAUFF |
| CofO Issued | 4/10/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/15/2025 | ALEXANDER HELFER |
| Address approval | Cleared | 4/1/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 4/1/2025 | JESSICA OPINION |
| "Q" conditions | Cleared | 4/3/2025 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2025 | JESSICA OPINION |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/11/2025 | Corrections Issued | LILIANA PORTILLO |
| Special/Order Compliance | 8/4/2025 | Partial Inspection | GEM DE OCAMPO |
| PLUMBING-Rough | 8/6/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/2/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 12/2/2025 | Corrections Issued | LILIANA PORTILLO |
| Wood Frame | 12/2/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/20/2026 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 1/20/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/20/2026 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 1/20/2026 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/23/2026 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 1/23/2026 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/23/2026 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 1/23/2026 | Approved | LILIANA PORTILLO |
| Shower Pan | 1/23/2026 | Approved | LILIANA PORTILLO |
| Insulation | 1/30/2026 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/30/2026 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2026 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 2/10/2026 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/1/2026 | Approved | LILIANA PORTILLO |
| Final | 4/1/2026 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 4/1/2026 | Approved | LILIANA PORTILLO |
| Green Building Rough | 4/1/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/1/2026 | SGSOV No Gas | LILIANA PORTILLO |
| Smoke Detectors | 4/1/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/8/2026 | Approved | LILIANA PORTILLO |
| Final | 4/8/2026 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 4/8/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 4/8/2026 | Approved | LILIANA PORTILLO |
| Service/Power Release | 4/8/2026 | Approved | LILIANA PORTILLO |