1932 S 10TH AVE 90018
Certificate Information: 1932 S 10TH AVE 90018
- Application / Permit
- 25016-10000-03345
- Plan Check / Job No.
- B25LA04644
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- CONVERT LUNCH TENT INTO MULTI-PURPOSED ROOM, ACCESSORY TO CHURCH USE ON SITE
- Permit Issued
- Issued on 11/4/2025
- Issuing Office
- Metro
- Current Status
- Issued on 11/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/6/2025 | APPLICANT |
| Assigned to Zoning Architect | 2/6/2025 | SARHAD GHEVANDIAN |
| Assigned to Plan Check Engineer | 2/27/2025 | JOE VO |
| Corrections Issued | 3/13/2025 | JOE VO |
| Quality Review Completed | 3/21/2025 | KEN GILL |
| Building Plans Picked Up | 4/15/2025 | APPLICANT |
| Disabled Access Plans Picked Up | 4/15/2025 | APPLICANT |
| Applicant returned to address corrections | 9/15/2025 | JOE VO |
| Plan Check Approved | 10/20/2025 | JOE VO |
| Issued | 11/4/2025 | APPLICANT |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 4/1/2025 | DAVID LOPEZ |
| Highway dedication | Cleared | 4/1/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 4/1/2025 | DAVID LOPEZ |
| Community Plan Implem. Overlay | Cleared | 4/11/2025 | BRANDON WONG |
| Bicycle Parking | Cleared | 6/27/2025 | ARNULFO CHAMU |
| ZA Case | Cleared | 7/16/2025 | ROSALINDA MEZA |
| ZA Case | Cleared | 7/16/2025 | ROSALINDA MEZA |
| ZA Case | Cleared | 7/16/2025 | ROSALINDA MEZA |
| ZA Case | Cleared | 7/16/2025 | ROSALINDA MEZA |
| CPC | Cleared | 7/23/2025 | ROSALINDA MEZA |
| ZA Case | Cleared | 7/23/2025 | ROSALINDA MEZA |
| ZA Case | Cleared | 7/23/2025 | ROSALINDA MEZA |
| Community Plan Implem. Overlay | Cleared | 8/5/2025 | IRA RODRIGUEZ |
| Green Code | Cleared | 8/20/2025 | MICHAEL MARTINEZ |
| Hydrant and Access approval | Cleared | 8/22/2025 | PATRICK PEREZ |
| DAS Clearance | Cleared | 9/9/2025 | JOE VO |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2025 | STEVE MELGAR |
| Sewer availability | Cleared | 9/10/2025 | STEVE MELGAR |
| Community Plan Implem. Overlay | Cleared | 9/17/2025 | ISAIAH ROSS |
| Zoning Plan Check | Cleared | 9/23/2025 | SARHAD GHEVANDIAN |
Contact Information
| Architect | Ko,, Michael Myungsoo; Lic. No.: C22356 | 3435 WILSHIRE BLVD #2905 LOS ANGELES, CA 90010 |
| Contractor | Morris Construction Inc; Lic. No.: 991317-B | 9502 BROCK AVE DOWNEY, CA 90240 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/6/2025 | Partial Approval | ALFREDO LOPEZ |
| Green Building Rough | 11/25/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Insulation | 11/25/2025 | Partial Approval | EDWIN GREGORYONA |
| METHANE-Rough | 11/25/2025 | Approved | EDWIN GREGORYONA |
| Wood Frame | 11/25/2025 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Partial Approval | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Partial Approval | MARTIN TAVITIAN |
| Special/Order Compliance | 1/8/2026 | Approved | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2026 | Partial Approval | IAN BLINN |
| Insulation | 3/20/2026 | Partial Approval | IAN BLINN |
| Interior/Exterior Lathing | 3/20/2026 | Partial Approval | IAN BLINN |
| Drywall Nailing | 3/24/2026 | Partial Approval | IAN BLINN |
| Final | 5/22/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Green Building Final | 5/22/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Green Building Rough | 5/22/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 5/22/2026 | SGSOV Not Ready | MARTIN TAVITIAN |
| Smoke Detectors | 5/22/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Wood Frame | 5/22/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 5/28/2026 | Not Ready for Inspection | IAN BLINN |
| Green Building Final | 5/28/2026 | Approved | IAN BLINN |
| Green Building Rough | 5/28/2026 | Approved | IAN BLINN |
| SGSOV-Seismic Gas S/O Valve | 5/28/2026 | SGSOV Not Required | IAN BLINN |
| Smoke Detectors | 5/28/2026 | Approved | IAN BLINN |
| Wood Frame | 5/28/2026 | Partial Approval | IAN BLINN |