427 E 61ST ST 90003

Certificate Information: 427 E 61ST ST 90003

Application / Permit
25016-10000-03255
Plan Check / Job No.
B25LA04473
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) 1-STORY SFD, ALL WORK PER WFPP
Permit Issued
Issued on 2/26/2025
Issuing Office
Valley
Current Status
Permit Finaled on 9/26/2025

Permit Application Status History

Submitted 2/5/2025 APPLICANT
Assigned to Plan Check Engineer 2/5/2025 MINA HABILI
Plan Check Approved 2/5/2025 MINA HABILI
Issued 2/26/2025 APPLICANT
Permit Finaled 9/25/2025 SABAS ALONSO

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Advanced Construction; Lic. No.: 801955-B 4606 WILLIS AVE #307      SHERMAN OAKS, CA 91403

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 3/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 3/6/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 3/6/2025 Approved ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 3/10/2025 Conditional Approval ANTHONY RAMOS
ELECTRICAL-Rough 4/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 4/14/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/14/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/25/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/25/2025 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/25/2025 Approved ALEJANDRO DE ARTOLA
Insulation 5/1/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/1/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 5/14/2025 Approved ANTHONY RAMOS
Shower Pan 5/14/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 5/30/2025 Approved ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Approved JOSH MEISTER
ELECTRICAL-Final 9/17/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 9/17/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 9/17/2025 SGSOV Approved BARRY HACHE
ELECTRICAL-Final 9/19/2025 Corrections Issued BRENDAN MORELLI
Final 9/19/2025 Not Ready for Inspection BRENDAN MORELLI
HVAC-Final 9/19/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 9/19/2025 Approved BRENDAN MORELLI
Smoke Detectors 9/19/2025 Approved BRENDAN MORELLI
ELECTRICAL-Final 9/24/2025 Approved SABAS ALONSO
Final 9/24/2025 Corrections Issued SABAS ALONSO
HVAC-Final 9/24/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Final 9/24/2025 Approved SABAS ALONSO
Service/Power Release 9/24/2025 Corrections Issued SABAS ALONSO
Final 9/25/2025 Permit Finaled SABAS ALONSO
HVAC-Final 9/25/2025 Approved SABAS ALONSO
Service/Power Release 9/25/2025 Approved SABAS ALONSO