1436-1436 1/2 S SPAULDING AVE 90019

Certificate Information: 1436-1436 1/2 S SPAULDING AVE 90019

Application / Permit
25016-10000-03245
Plan Check / Job No.
B25LA04461
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Interior remodel of existing duplex. Convert existing basement to an attached ADU per GCS 65852.2(e)(1)(C).
Permit Issued
Issued on 3/27/2025
Issuing Office
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2025 APPLICANT
Assigned to Plan Check Engineer 2/13/2025 MARCELA FRANQUEZ
Corrections Issued 2/25/2025 MARCELA FRANQUEZ
Quality Review Completed 3/5/2025 HERNAN ARREOLA
Plan Check Approved 3/26/2025 MARCELA FRANQUEZ
Issued 3/27/2025 APPLICANT
CofO in Progress 11/21/2025 ARTHUR NEGRETE
No Progress 11/22/2025 DEROLD HAUFF
CofO in Progress 11/22/2025 DEROLD HAUFF
CofO in Progress 1/28/2026 DEROLD HAUFF
Permit Finaled 1/28/2026 DEROLD HAUFF
CofO Issued 1/28/2026 DEROLD HAUFF
Permit Finaled 1/28/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/9/2025 RYAN CASTRO
Sewer availability Cleared 3/9/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/11/2025 RYAN CASTRO

Contact Information

Contractor Golden Age Builders; Lic. No.: 1040171-B       ,
Contractor Golden Age Construction Inc; Lic. No.: 1040171-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/21/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 5/30/2025 Approved ARTHUR NEGRETE
HVAC-Rough 5/30/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 5/30/2025 Approved ARTHUR NEGRETE
Shower Pan 5/30/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 6/4/2025 Approved ARTHUR NEGRETE
Green Building Rough 6/4/2025 Approved ARTHUR NEGRETE
METHANE-Rough 6/4/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 6/11/2025 Approved ARTHUR NEGRETE
Drywall Nailing 6/11/2025 Approved ARTHUR NEGRETE
Green Building Rough 6/11/2025 Approved ARTHUR NEGRETE
Insulation 6/11/2025 Approved ARTHUR NEGRETE
Final 9/16/2025 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 9/16/2025 Not Ready for Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 9/16/2025 Approved ARTHUR NEGRETE
Final 11/21/2025 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 11/21/2025 Approved ARTHUR NEGRETE