1457 N VAN NESS AVE 90028
Certificate Information: 1457 N VAN NESS AVE 90028
- Application / Permit
- 25016-10000-03115
- Plan Check / Job No.
- B25LA04253
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR OFFICE T.I. FOR OFFICE. WORK TO INCUDE NEW WALKWAYS, PARTITIONS, CEILING, AND FINISHES.NO NEW SQUARE FOOTAGE IS BEING ADDED (1,352 GROSS SQUARE FEET).
- Permit Issued
- Issued on 4/24/2025
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 7/17/2025
Permit Application Status History
| Submitted | 2/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2025 | LUKE GONZALES |
| Corrections Issued | 2/5/2025 | LUKE GONZALES |
| Building Plans Picked Up | 2/7/2025 | APPLICANT |
| Plan Check Approved | 4/15/2025 | SAMUEL GONZALEZ |
| Issued | 4/24/2025 | APPLICANT |
| Permit Finaled | 7/17/2025 | LUIS CCAMACHO |
Permit Application Clearance Information
| CPC | Cleared | 2/18/2025 | ROSALINDA MEZA |
| CPC | Cleared | 2/18/2025 | ROSALINDA MEZA |
| CPC | Cleared | 2/18/2025 | ROSALINDA MEZA |
| CPC | Cleared | 2/18/2025 | ROSALINDA MEZA |
| ZA Case | Cleared | 2/18/2025 | ROSALINDA MEZA |
| City Hist. Cultural Monument | Cleared | 2/20/2025 | RAFAEL FONTES |
| Historic Resource Verification | Cleared | 2/20/2025 | YASMINE BASHIRI |
| Historic monument | Cleared | 2/20/2025 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 2/20/2025 | YASMINE BASHIRI |
| Address approval | Cleared | 3/6/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/6/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Holwick Constructors Inc; Lic. No.: 766151-B | 200 N WESTLAKE BLVD SUITE 102 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 5/15/2025 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 5/28/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 5/30/2025 | Partial Approval | TIMOTHY POWELL |
| T-Bar Ceiling | 6/27/2025 | Approved | EDWIN GREGORYONA |
| Final | 7/17/2025 | Permit Finaled | LUIS CCAMACHO |
| Reinforced Masonry Frame | 7/17/2025 | Approved | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 7/17/2025 | Approved | LUIS CCAMACHO |