3263 S WOODBINE ST 90064
Certificate Information: 3263 S WOODBINE ST 90064
- Application / Permit
- 25016-10000-03112
- Plan Check / Job No.
- B25LA04249
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: INTERIOR REMODEL TO (E) SFD AND ATTACHED JADU TO CREATE THREE (N) CLOSETS FOR BEDROOMS, REMODEL BATHROOMS, AND CREATE (N) LAUNDRY.
- Permit Issued
- Issued on 2/20/2025
- Issuing Office
- Current Status
- Permit Finaled on 8/8/2025
Permit Application Status History
| Submitted | 2/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2025 | KAMYAR EMAMI |
| Corrections Issued | 2/10/2025 | KAMYAR EMAMI |
| Plan Check Approved | 2/19/2025 | KAMYAR EMAMI |
| Issued | 2/20/2025 | APPLICANT |
| Permit Finaled | 8/7/2025 | MEL KHACHATOURIAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/13/2025 | VASIL MIHALEV |
Contact Information
| Contractor | Green Roomers Inc; Lic. No.: 927982-B | , |
| Engineer | Rhee,, Kyle; Lic. No.: NA78215 | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/30/2025 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 5/2/2025 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/9/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 5/9/2025 | Approved | BOBBY KEY |
| HVAC-Rough | 5/9/2025 | Approved | BOBBY KEY |
| MERV13>=Rough | 5/9/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 5/9/2025 | Partial Approval | BOBBY KEY |
| Insulation | 5/13/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 5/13/2025 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 5/19/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 5/19/2025 | Approved | ASHLEY THOMPSON |
| Shower Pan | 5/19/2025 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Not Ready | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 8/1/2025 | SGSOV Not Ready | STEPHANIE SWANSON |
| Final | 8/7/2025 | Permit Finaled | MEL KHACHATOURIAN |
| MERV13>=Final | 8/7/2025 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 8/7/2025 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 8/7/2025 | Approved | MEL KHACHATOURIAN |