7024 S BONSALLO AVE 90044
Certificate Information: 7024 S BONSALLO AVE 90044
- Application / Permit
- 25016-10000-03067
- Plan Check / Job No.
- B25LA04204
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL OF 7024 BONSALLO KITCHEN, BEDROOMS, BATHROOMS
- Permit Issued
- Issued on 2/27/2025
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/26/2025
Permit Application Status History
| Submitted | 2/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2025 | SUNMIN LEE |
| Corrections Issued | 2/4/2025 | SUNMIN LEE |
| Plan Check Approved | 2/27/2025 | JOHN MESIAS |
| Issued | 2/27/2025 | APPLICANT |
| Permit Finaled | 11/25/2025 | BARRY HACHE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 2/7/2025 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 6/16/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 6/16/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 6/16/2025 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 6/23/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 6/23/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 6/23/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 6/23/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 6/30/2025 | Partial Inspection | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 7/2/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 7/2/2025 | Approved | BARRY HACHE |
| Insulation | 7/14/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 7/17/2025 | Corrections Issued | BARRY HACHE |
| Drywall Nailing | 7/21/2025 | Approved | RONNIE MEDINA |
| Shower Pan | 8/8/2025 | Corrections Issued | BARRY HACHE |
| Interior/Exterior Lathing | 8/12/2025 | Approved | BARRY HACHE |
| Shower Pan | 8/12/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 8/25/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 8/27/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 11/10/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 11/13/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 11/13/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 11/17/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 11/17/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 11/17/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 11/24/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Final | 11/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 11/24/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 11/24/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/25/2025 | Approved | BARRY HACHE |
| Final | 11/25/2025 | Permit Finaled | BARRY HACHE |
| PLUMBING-Final | 11/25/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 11/25/2025 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 11/25/2025 | Approved | BARRY HACHE |